REA Final - 22 Dec 20 - eBook - 1682 pages
Spearhead Field Notes - PBB
Date
Issue
Field Note
Additional Notes
2020-02-01 Production Loss - SWJV - Steel 2020-02-01 Comeback - SWJV
bq boo; ceilign dropped, see previous note 29 jan 20
Unable to access this area to install sheet rock 4th FL in 4 areas (BOH at sharft wall, elevator control room, elevator door fronts, west wall towards BOH)
Waiting on inspection; reassigned: boards installers; could have sent 2 guys per 4 areas (8 guys reassigned); rock 1 day per area (double layers) 8 hours- lost 10% production waiting for inspections and reassigning men to other areas… waited 2 weeks (11 days) - see email 2 feb 20
2020-02-03 Production Loss - Waiting on Others 2020-02-04 Comeback - SWJV 2020-02-04 Production Loss - SWJV - Steel
Flowbar issue
Control joints 5 total had to comeback to tape CEILING
taper had to come back 2 times
BQ 00 steel 2" off center, bolts in the way; had to shave back of GFRG; later, had to comeback w taper to modify further; installed as high as it could go
Taper had to fix the radius of that curve to make it work after ceiling lowered and also the bolts in the way; 2 guys took 4 hours to make fit over bolts, taper took 3 visits to build up compound (2 hrs each time) just to make smooth curve
2020-02-05 Damage - by Others 2020-02-05 Comeback - Waiting on Others
Damage done to the column on the B2Line
carpenter 1 hr and taper 2 hours
Spearhead is still waiting for flow bars to be in stalled so they can be taped in.
ceiling already skimmed; 1 taper took 3 days to do each side (mesh) = 3days x 4 trips = 12 days total or 96 hours
2020-01-21 2020-01-21
For January 12, 2020
sheetrock to slope NorthWest side
2020-02-08 Comeback - Trade Interference
We are waiting for light fixtures @capitals on the Eastside beween four and five
we had to comeback to install sheetrock after we had already sheetrocked the cove; see marks on FRG Capital showing where we had anticipated lights; at each location, the time lost was (42 lights at cove area only comeback.. 2 per area... therefore, 21 times)… had to do cove, then back and then the flat part for lights (3 comebacks) (we calculated based on 3 guys for 1 entre week - 5 days to sheetrock for lights after they got set: 8*5*3=120 hours PLUS we were delayed while we waited for those lights... had to reassign workers, lost 10% productivity while we waited... wait time started on 23 Jan... waited 16 days so far to finish this rock