REA Final - 22 Dec 20 - eBook - 1682 pages
Spearhead Field Notes - PBB
Date
Issue
Field Note
Additional Notes
2020-02-08 Comeback - Trade Interference
out of sequence - comeback work to sheetrock back of soffiits separately because waiting on sprinkler
we had to comeback to install sheetrock at backside of soffit; at each location, the time lost was 5 days for 3 guys to cover the soffits for (14 bays)… had to do cove, then back soffit and then the flat part for lights (3 comebacks)… harder area to get to... bigger boards, less productivity due to location 2 to 3 days to add framing and sheetrock to mount fire alarms to get inspected only 1 out of 20 lights in place at this location on 8 feb… by 13 feb, only 7 out of 20 lights installed (meaning it took 5 days to install 6 lights); sequence was to be: frame (done), electricain install lights, inspect lights, then rock
2020-02-08 Production Loss - SWJV - No Schedule 2020-02-08 Production Loss - Waiting on Others
Fire alarms sheetrock for inspections (see bill's diagram)
waiting for lights in ceiling - ALL LIGHTS AT COVE
2020-01-22 2020-01-22
diner ceiling
Hayden Jamal and Matthew are installing core board on the back of the duct shaft on the third floor
2020-01-23 2020-01-23 2020-01-24 2020-01-24
diner ceiling
24th of January 2020 sign in sheet ceiling grid install that Northwest flare
took time to fine a clean area for them to work
insulating and sheetrocking the loading platform wall hole to remain open. 1st coat complete. Diner SE.
2020-02-12 Comeback - SWJV 2020-02-12 Comeback - Trade Interference 2020-02-12 Comeback - SWJV
1 hour for boad, 1 hr for bead, 3 hours for tape to level 5 finish
1str Area GFRC base not ready to install
HAD To comeback to install GFRC not ready
hole at mech room (wall by fire alarm/double door to BOH) Merrick is installing corner bead on the square columns he's on the third column,two are complete finishing the third Damage to wall at Brooklyn Diner. Spearhead will have to repair. Area on east wall at north access panel.
1 hour for boad,
2020-01-24
2020-02-12 Damage - by Others
1 hour to repair; already skim coated, have to come back 15 mins each time w finisher (4 times including polish)
2020-01-24 2020-01-26 2020-01-26
sheetrockin the ceiling in the diner Brooklyn Diner pedestrian bridge b
pedestrian bridge b
2020-02-17 Production Loss - SWJV - Work Stoppage
SWJV directed SpCX to stop intall of GFRC bases; Toe Kick issue needs to get sorted out