REA Final - 22 Dec 20 - eBook - 1682 pages

Spearhead Field Notes - PBB

Date

Issue

Field Note

Additional Notes

2020-01-18 Production Loss - SWJV - Work Stoppage

Work Stoppage - lost 1 shift for Load Test Saturday 18 Jan 20

2020-01-11 2020-01-11

Framing wall south of fire panel room on Northwest flare Goal is to frame in rock square columns on south east of building bridge Wrapping up the elevator door bucks on level III. These door box or a problem due to the white tube steel that was proud of the rated wall. Extremely difficult to get scoreboard and set up for double layer. Zack Trausse directed Spearhead to bring the two layers of rock to it but the tube steel. Then we will fire caulk around it. Work Stoppage - lost 2 shifts for Load Test Sunday 19 Jan 20 (LEVEL 4) FRG's column base on the BQ line I am in column number one probably damage while moving sand on the 19th or 18thAnd damage FRG soffits probably damage on the same day Wrapping up the elevator door bucks on level III. These door box or a problem due to the white tube steel that was proud of the rated wall. Extremely difficult to get scoreboard and set up for double layer. Zack Trausse directed Spearhead to bring the two layers of rock to it but the tube steel. Then we will fire caulk around it. EXAMPLE OF BASES NOT LINING UP W FLOOR SLOPE AND SLAB SINKING

2020-01-19 Production Loss - SWJV - Steel

TUBE STEEL SUPPOSED TO BE WITHIN SHAFT WALL; HAD TO COREBOARD AROUND IT, BEHIND IT TO SEAL IT;

2020-01-19 Production Loss - SWJV - Work Stoppage

2020-01-20 Damage - by Others

2020-01-20 Production Loss - SWJV - Steel

TUBE STEEL SUPPOSED TO BE WITHIN SHAFT WALL; HAD TO COREBOARD AROUND IT, BEHIND IT TO SEAL IT;

2020-01-20 Production Loss - SWJV - Steel

2020-01-11 2020-01-11 2020-01-11 2020-01-11 2020-01-13 2020-01-13 2020-01-13 2020-01-13

Inside area between drywall and AC T

Laminated steel inside elevator shaft complete fourth floor Need to add 3 foot wall from diner back to curtain wall

Wall at diner

ceiling grid in diner

January 13th 2020 night shift

Leroy, shooter , and figgy sheetrocking the fire alarm room South East wall in the diner and ceiling grid, also rocking the columns