Spearhead Field Notes - PBB

Date

Issue

Field Note

Additional Notes

2020-01-03 2020-01-03 2020-01-03 2020-01-05 2020-01-05 2020-01-07 2020-01-07 2020-01-07 2020-01-08 2020-01-08 2020-01-08 2020-01-08 2020-01-10 2020-01-11 2020-01-11 2020-01-11 2020-01-11 2020-01-11

Phil and Matt the shop steward on the fire shutter wall these are the front FRG capitals over the moving walkway

this is the b r line 4th floor diner

Andre and Merek didn't come in

FRG capitals over the moving walkway a done up to col 3 taping columns on the 4th floor Carlos Rodriguez you started making up the light pocket on the fourth floor and installing it

capitals at the br line

install the last of the capital over the moving walkway

January 8, 2020 sign in sheet

well at the southeast corner by the duct shaft

trusses have to BR line

Black Iron installed along West curtain wall

Black Iron installed at elevator.

Black Iron installed from column line 2 / 1 to dance floor.

Black Iron installed onWest curtainwall side

Call 8 be

2020-01-16 Production Loss - Congestion

still very congested

PORTO JOHNON SITE AGAIN

2020-01-11

Column line 8

2020-01-16 EXTRA - DIRECTED

SEISMICWIRES AT GYP CEILING Diner wall nearing completion SEISMICWIRES AT GYP CEILING

24 REGULAR (2ND SHIFT) + 10 OT

2020-01-11

2020-01-17 EXTRA - DIRECTED

24 REGULAR (2ND SHIFT) + 4 OT; COMPLETE ANDWAITING FOR INSPECTIONS

2020-01-18 Damage - by Others

[Damaged GFRC base at Col BQ 0] Zero damaged base call online zero going to one.Appears to of been rammed with a forklift Building still not weather tight. Rain coming in at Square column on south east corner of Bridge. Between column nine and eight. MR board soaking wet.

2020-01-18 Damage - by Weather