Spearhead Field Notes - PBB

Date

Issue

Field Note

Additional Notes

2020-01-06 Production Loss - Congestion 2020-01-06 Production Loss - Equipment "down"

it's even worse than before

2nd shift, 15 guys- CONGESTION

second spider lift is does not move we're only using one spider left we're hoping to use to to finish the backs of the capitol

50% production due to 1 out 2 spiders working

2019-12-18 2019-12-19 2019-12-23 2019-12-26 2019-12-27 2019-12-27 2019-12-29 2019-12-30

column line br trust number 8

BR column line trusses 6 7 and 8 capitals

Kone working very hard in all their PPE… while everyone is working around them. does not appear they have much of a fire lit.

FRG based on column 9

cleaned up the diner at the flare Southeast corner

Dayshift 12/27/19

can Kennedy Robert Johnson in AJ doing the black iron in the diner

Merrick and Andre working over the moving walkway

2020-01-09 Production Loss - SWJV - No Schedule

how is this going to be finished? every wall is Sheetrock in the staircase and they put the one rail in where it's not Sheetrocked or finished going to be working night shift they took both bathrooms down had to walk down 15 minutes for people to go to bathroom the gfi's aren't working and the light is still poor

2020-01-10 Production Loss - SWJV - Work Stoppage

Bathrooms moved far away; far west part of builing, outside on level 2; took 15mins each way to get to

2019-12-30

Steve gerina and Tom are doing black iron in the diner

2020-01-11 Production Loss - Trade Interference

Fire panel room. Kindred in way of rated wall. Gary notified Bill. Needs to be pushed back or this will be extra work to fix due to rating.

Day 1 - Fire Panel Rm; had to notch track and board to account for fire- rating

2020-01-11 Production Loss - Trade Interference 2020-01-11 Production Loss - Trade Interference 2020-01-11 Production Loss - Trade Interference

Level two Dash Kindorf in the way of wall. Excess Kindorf.

Day 1 - Lvl 2

Level two pipe directly were wall is supposed to be. pipe needs to be pulled out Paul [Pole] hanging down for monitor at column line 6. Will be in our way as we install rock.

DELAY by others - No coordination of pipe where Wall is supposed to be; had bump out wall to get around pipe (never moved) OUT OF SEQUENCE; NO COORDINATION -slowed productivity trying not to hit obstacle that was installed too soon (prior to soffit framing)

2019-12-31 2020-01-02 2020-01-03 2020-01-03

doing capitals over the walkway

American Anthony working over the moving walkway B3-B2

loading material on to the third floor