REA Final - 22 Dec 20 - eBook - 1682 pages

Spearhead Field Notes - PBB

Date

Issue

Field Note

Additional Notes

2019-12-09

trust from 8 to 7 has 12 pieces of sheetrock installed, trust from 6 to 5 has eight pieces of , col. from 4 to 3 has 12 pieces sheetrock install, truss 322 has 12 pieces install. these are sheetrock legs it says we got 20 pieces on the ticket I count 18 coreboard

2019-12-12

2019-12-30 Production Loss - Weather

roof is still leaking this is the southeast in the diner

2019-12-12

Kevin Charles first a today Mike Rizzo ,Tom O, Riley Andre Lewis are out today we just talked about putting ducks [duct] in our way so we can be productive and get done quicker this is what just happened today and they knew we need the pipes were in Iowa it's going to move those in so we can build a wall now they put a duck in our way how do we rate that wall behind the duct

2019-12-30 Production Loss - Waiting on Others

CEILING in Stairway: Access was inredibly difficult due to platform in the way of building up wall; conduits in the way, could not build wall until conduits moved; had meeting prior to conduits going in; info did not relay back to other forman; they were directed to tie to steel not in front of fireproofing. 6" wall had to shrink down to 4" due to steel and conduits on west side (at landing), staircase was 6"; had to work around duct (OUT OF SEQUENCE) to get ceiling tied in; wall inspections and ceiling inspections; as access became available, 5 times (4" wall, back wall, east wall (off platform), 6" west wall, ceiling) inpecitions for each piece x3 => 15x w inspecitons! PLUS patchiong of walls where chians were

2019-12-12 2019-12-14

received a delivery today from kamco 6 column line br capitals from 8 to 7 and 7 to 6

2020-01-02 Production Loss - Weather

the bridge is still wide open

2019-12-14 2019-12-14 2019-12-14

Anthony and Nick on the panel Max machine

bringing up to level five board

soffit framing

2019-12-14 what is this?

No work for Black Iron

2019-12-14 2019-12-16

these are concrete bases at column 8

soffit framing at B3-B4

2020-01-05 Production Loss - Congestion

the diner is packed solid with lifts and garbage

CONGESTION right where we need to finish ceiling in B'Diner

2019-12-16 2019-12-17

trusses west side

Carlos Rodriguez taping trusses