REA Final - 22 Dec 20 - eBook - 1682 pages

Spearhead Field Notes - PBB

Date

Issue

Field Note

Additional Notes

2019-12-03 verify time lost

booming up frg for the 4th floor campco today have today also

2019-12-03

2019-12-27 Production Loss - Weather

building still open exposed to the weather

2019-12-04 2019-12-05

northwest corner

December 5th 2019 timesheet

2019-12-28 Comeback - Waiting on Others 2019-12-28 Production Loss - SWJV - No Schedule

3rd floor NW corner Showing obstacles for us to put final board up following Cord's completion on the exterior. third floor exterior wall we still have to rock the high impact on the back of cords wall that was just installed and this all mechanicals in the way

End - Cord

DAY 1 - Mechanicals; lost 100% due to OUT of SEQUENCE with tin knocker before wall jup

2019-12-28 Production Loss - Weather 2019-12-28 Production Loss - Weather 2019-12-29 Production Loss - Congestion 2019-12-29 Production Loss - 2019-12-07

28 Dec still opened building

28 Dec still opened building

this is the quarter inch joint at the base and the leg at the trust fourth floor tech ridge b congested can't access ceilings

re-assign black iron

shooter and Leroy doing this coreboard shaft in the diner

difficult to access from back

Restricted Movement

2019-12-30 Production Loss - SWJV - Work Stoppage

L2 weatherwall still mostly in place. cannot tie into with still in the way.

Continued promises to open up access to Levels in BOH (Level 2); cannot work in these areas; if we got stuck upstairs/ or blocked off due to congestion, could not reassign workers to this area; inefficient/ delayed scheudle;

2019-12-30 Production Loss - Waiting on Others 2019-12-30 Production Loss - Waiting on Others 2019-12-30 Production Loss - SWJV - No Schedule

elevator fronts not ready yet. 4th floor. kone off until friday.

Mon thru Fri (4 days)

fire shutter not in yet, can't start framing without them being complete. furred out wall "can be ready for us" when we want. not currently ready yet.

waiting on others to get their steel in place

need layout p+ 3 guys to do top track and bottom legs/ 1 guy cutting studs

2019-12-09

trussing en closure from the outside looking east