Date
Issue
Field Note
Additional Notes
2019-11-24 2019-11-24 2019-11-24
they started to build the platform above the escalator this is the elevator control room on the fourth floor
we're continuing to work on the wall on the third floor completing the 3-hour wall we can't frame these columns they have to be x-rayed we were directed to hold off
2019-12-17 Production Loss - SWJV - Work Stoppage
Cannot work here even if they hadn't cut studs and scraped fire proofing;
2019-11-29
the shop stewarf left after 2 hours so he's getting paid for 2 hours today, Gauntlet holness
2019-12-17 Production Loss - Rework
column before they cut the stud out to x-ray the beam
comeback work to repair studs and clips that were removed for xray; had to wait until they cleared / approved the steel; they knew something was concerning to actually pay to have steel x ray, had to set studs, and clips (4 legs); removed damaged pieces, patch stud in and resupport stud, reshoot clips and then install the stud
2019-12-17 Damage - by Others
column five damaged by other trades need to replace the stud Steve Gerena installing black iron over the walkway this is the left side of truss 3 damaged also has to be replaced
used track to speed up damage repair at truss 3 and 5
2019-12-17 Progress
2019-12-17 Damage - by Others 2019-12-17 Damage - by Others 2019-12-18 Damage - by Others 2019-12-18 Damage - by Others 2019-12-18 Production Loss - Congestion 2019-12-18 Production Loss - Congestion 2019-11-29
accounted for with col 5
truss 3 damaged stud needs to be replaced black iron over the walkway got damaged by Sirina Working on Capitals, Anthony and Merek patch in the staircase at the top of the third floor
damage
trust number 7 Stud was cut out to install steel at the restaurant col 8 also col 9 we couldn't work over the moving walkway Sirina had the lift till six 6:30 and then they took the key so no one could use the lift
took 1 full day to get on lift to reach; congestions
had to reassign workers to different location due to lack of access; had to clear out space and had to move other trades stuff out of way; needed lathers to set lines in order to set our capitals which held us up to do our install of gfrg
2019-11-30
Andre and Joe eckert on the scissor lift
2019-12-19 Production Loss - Congestion
still very congested up here
completely congested; getting worse
2019-11-30 2019-11-30
Simon and figgy on the boom lift on the third floor
we were able to make use of the boom lift and the scissor lift from the outside to complete the rest of all walls