REA Final - 22 Dec 20 - eBook - 1682 pages

Spearhead Field Notes - PBB

Date

Issue

Field Note

Additional Notes

2019-12-13 Production Loss - Congestion

very congested from B -2 North

congested; taper cannot get in there to 2nd coat while others started installing pipes and kindorf; OUT of SEQUENCE; installing before wall taped/finished; had to work around them; stop and start tape, stop and start knoife; inefficient for taping; had to comeback and now there are pipes on the wall; plus we had to reassign taper to other area

2019-12-14 Production Loss - Congestion 2019-12-14 Production Loss - Weather

still very congested on the 4th floor

there's still some water coming in on the NorthWestside

2019-11-17 2019-11-17

we.are working on the FRG capitals the fourth floor

working on the 4th floor extra work and finishing contract chef for work above the elevator doors

2019-11-18 2019-11-21 2019-11-23 2019-11-23 2019-11-24

Cleaned up Shannon

starting to install level 5 sheetrock at trusses this is the tapered splay at one of the trusses

what boomin some Sheetrock up to the second floor and core board

she rocking the 3-hour wall extra work from the outside

2019-12-16 Comeback - Waiting on Others

high impact board on the Southeast wall

had to comeback after fire proof inspection; had to hold up boards which prevented us from doing stand up installation; took another 4 hours to comeback and fill bottom piece; changed the wall type from 0 rated to 2hr which included 2hr clips; directed to rock tight to cord's clips that were attached to sgtructural steel then stuff with insulation and taped and spackled; inspector did not sign off on that which had taken way too long; plus, there was a duct hanging down unconnected, right in the way that we had to work around and remained like that for 4 weeks; we ultimatlely added a box header to cover this steel in order to rate th wall. entire length took 1 week for boards + 1 week for box header + we had to seal the soffit to the top steel (not our work) in order to rate the wall (1/2 a week); had to stand on the beam; hard to access; worked on 3 wknds as well (also, kindorf in the way and we had to wait for them to decide to cut out; waited nearly 2 weeks; we refused to move forward until that was out; mac tried to tell gary that there's always kindorf in rated walls, pfffft)