2020-02-11
All of the additioanl work done on the SE cornger. This was supposed to be furred out wall
already accounted for
2019-12-04 Production Loss - Weather 2019-12-04 Production Loss - Trade Interference
bridge still leaking
moving walkway
2019-11-02
elevator shaft is almost complete
MOVINGWALKWAY ON SITE (image shows MW all covered in layout area)
2019-11-23
finishing up the 3-hour wall on the outside of the second floor
previously accounted for
2019-12-05 Production Loss - Waiting on Others
from B2 North no access
could not install black iron (1); could not install capitals (4 guys); 5 reassigned; assigning 4 guys to areas where we already had crews, we lost 50% production efficiency
2019-12-05 Production Loss - Congestion
still very congested by the moving walkway
2019-12-06 Comeback - Waiting on Others
still very congested by the moving walkway
4 guys on 3rd floor leaving 5 guys on lvl 4
2019-10-27
third floor back of house
2019-12-07 Production Loss - SWJV - No Schedule
close off staircasecase to put concrete (BOH contract)
could not access level 3 due to entire staircase getting concrete pour (4 guys x 8 hrs ea = 32 hours); told 2 guys not to come in, other 2 reassigned which took an hour to get them set up
2019-12-07 Production Loss - Congestion
still congested up here but what continue now the capitals in legs and what started the soffit framing a sheetrock still on the ground floor deliveredWednesday it's Saturday today
2019-12-07 Production Loss - SWJV - No Schedule
4 days so far that we do not have critical work; we planned our deliveries to arrive just in time; we were running low on boards; inexcusable
2019-10-28 2019-10-29
FRG Columns
FRG columns from the outside
2019-12-07 Production Loss - SWJV - No Schedule
this the high impact board off of cords wall at the fire alarm room OUT of SEQUENCE work; fire alarm panel conduit in the way; installed prior to CORD's framing and we had to work around them to install boards; impact to productivity.
2019-10-29
third floor pedestrian bridge