REA Final - 22 Dec 20 - eBook - 1682 pages
Spearhead Field Notes - PBB
Date
Issue
Field Note
Additional Notes
2020-01-02 Production Loss - SWJV - No Schedule
this is howmuch that comes out of plump
THIS IMAGE! - Capital cannot even hit stud because truss is so far out of plumb; had to add 90 angle just to attach capital VERIFY LOSS OF PRODUCTIVITY' had to modify framing due to gusset plate from 6" to 2.5" off 3 tier bakers; protect escalator, concrete at top not even poured yet; could not walk on concrete slab since it hadn't been poured; 60 ft down on other side; uneessary risk to our workers; could have used "window washers" scaffold; safer WAITED 8 DAYS to do this work (seen note 30 Dec 19); 2 guys day shift, 2 guys night shift
2019-11-27 Production Loss - SWJV - Steel
continuing the wall at the escalator
2020-01-08 Production Loss - SWJV - No Schedule
framing wall at the fire alarm room
2019-12-06 Production Loss - SWJV No work for Black Iron 2019-12-07 Production Loss - SWJV No work for Black Iron 2019-12-08 Production Loss - SWJV No work for Black Iron 2019-12-11 Production Loss - SWJV No work for Black Iron 2019-11-30 Production Loss - SWJV - Steel
Between column seven and six: it's very possible the East side (BR) is going to be the same issue. Columns/trusses are not plumb. Bolts are causing Gfrg capitals to be out of plumb by as much as 1/2" to 3/4." If bolt threads (shown as sprayed yellow tips) can be cut by 1/2" , it would straighten the GFRG. The outside bolts covered by gfrg could be filed down w grinder. Not as bad. Unchanged, the difference is going to be noticeable. Need decision from SWJV in order to proceed. This particular area has been rebuilt three times already.
accounted for framing separately; bolts: 1 day to install GFRG; this was 3rd time and we had to do a total of 4 times; 4 days 92 guys)
2019-12-12 What is this? 2019-12-13 What is this?
No work for Black Iron No work for Black Iron
2019-11-30 Production Loss - SWJV - Steel
String is @ ceiling height. Unclear where fireproofing stops at bottom of plate/gusset plate on Column B7 and B6 at East side (BR) column line.
steel and FP issue tp solve
2019-12-15 what is this?
No work for Black Iron
2019-12-02 Production Loss - Trade Interference
moving walkway still isn't installed
2019-12-19 what is this?
no work for Black Iron
Made with FlippingBook - professional solution for displaying marketing and sales documents online