REA Final - 22 Dec 20 - eBook - 1682 pages
Spearhead Field Notes - PBB
Date
Issue
Field Note
Additional Notes
2019-11-21 Production Loss - SWJV - Steel
we are continuing installing gfrc column base
Comeback work; rebuilt mock up 4 times: (bolts Backwards)
2019-11-29 Production Loss -
installing flat metal for blocking for over the escalator
Restricted Movement
2019-11-29 Production Loss -
insulating the back of the escalator wall from the boom
Restricted Movement
2019-11-26 verify time lost 2019-11-24 Production Loss - Weather
morning stretch and flex
15 mins every day for every guy
Lots of wet Sheetrock on Level 4 and in Panelmax "shop"
h20 damage: sheetrock got wet, we had to restack sheetrock, not weathertight, drying out panelmax room, leaking from roof and open walls, wide open at escalator and other leaking areas; 1.5 days for taper to repair later
2019-11-24 Production Loss - SWJV - No Schedule
finished sheetrocking 3-hour wall on the third floor from the outside
we could have built entire wall from the inside
2019-11-21 verify time lost 2019-11-21 verify time lost 2020-01-15 verify time lost
FRG Column at the truss
building framing to hoiset mw into place finally started installing MW on 21st!
they're in the process of installing a walkway
3 conduit black Pipe are low, also there's mechanical hits above the escalator. Made skanska aware.
LAYOUT OVER ESCALATOR ID'd hits; lost time waiting to attach string… ultimately had to run offset string because we couldn't keep waiting; raised string 6" to continue to install black iron while waiting for pipe to be removed; had comeback to install black iron until pipe was removed; also framed ceiling up to pipe and had to comeback in order to let them remove the pipe. ANGLE WHERE CEILING SLOPED NEEDED 2 POINTS AND ALSO 2 POINTS AT ELEVATOR. 3 GUYS DOING LAOUT AND PUTTING UP STUDS TO PUT UP OURMARK SO GERENA COULD PULL HIS STRING FOR BLACK IRON
2020-01-17 verify time lost
framing wall by the loading platform
NO MORE PORTOJOHN
2019-11-25 Production Loss - SWJV I just found out there was a dimension bust in the moving walkway and they going to have to cut concrete so the moving walkway will not be done today 2019-11-25 Production Loss - Rework Serena's going back to put seismic on their sprinkler system and damaging some of our iron after they told her we were good to go there going back an putting in seismic in now
damage Black iron took additional week to repair (2 guys 5 days) w unreliable spiders
2019-11-25 Production Loss - SWJV - No Schedule
we're able to jump on the boom lift when the Ironworkers went to lunch and we're doing the fire tape
had to use boom to access work (tape back of wall)
Made with FlippingBook - professional solution for displaying marketing and sales documents online