REA Final - 22 Dec 20 - eBook - 1682 pages
Spearhead Field Notes - PBB
Date
Issue
Field Note
Additional Notes
2019-11-15 Production Loss - SWJV - No Schedule
we've been trying to get our sheetrock up/2 hours now the Maggie's wheels don't work then they do work you got all the block in the way, very difficult to load the plumber put his half inch copper pipe in the way of any materials getting in so it was took 3 hours to get on delivery up after work which in reality should only took 1 hour
Gary's favorite delivery noon arrival got pushed to 4pm (4 hours); lost productivity thinking we'd get down there, "soon";material on site earlier in day. Tarmac dug out making extreme difficulty getting materials to our guys. Then, a random copper pipe (1/2") installed right in the middle of the landing for all trades to have to negotiate. No walls up, could have put that pipe in at a different time. should have taken 1 hour to unoloed; took 3x as long;delay waiting to get materials that had arrived earlier DAY 1 - MW - Congestion at MW; we ramptued up to meet condencesed scheudle but then you plocked the area; 80% of east side not accesssible; all tool boxes had to be moved to west side, furthering congestion; only places we could work got stacked wmaterials and equipment; blocked east side of bridge plus still open where deliveries had been coming in on the north end; BEGINNING of delay fo rwast side work; further delay of scedule; could not add manpower even if we wanted to twork on east side from brooklyn diner north schedule trhown off- inability to schedule manpoer we loaded the job with painters to accelerate the taping so the painter could begin… eventhough we had no schedule that showed us when the painter was supposed to start… 10 out of 15 tapers impacted by congestion, 2 carpenters also impacted by trying to install control joints... moving East toWest across all the obstacles in the way... damaged rock; hit trash contaier
2019-11-16 Production Loss - Congestion
4th floor waiting for the moving walkway to be installed
2019-11-16 Damage - by Others
we were able to borrow at boom left so I doing accessing the second floor finishing are sheetrock
2020-02-17 Production Loss - SWJV - No Schedule
right under our sheetrock ceiling
2019-12-30 EXTRA - DIRECTED 2020-02-11 EXTRA - DIRECTED
review schedule for wrap up of job
Ainsworth and Gary attended all SpCx Collaboration meetings
add'l work directed by tej and mack cut opening ofr electric boxes needed. Should have been coordianted prior to install. Come back work needign ticket when complete. 2 days 2 guys total.
2019-12-10 Production Loss - Congestion 2019-12-11 Production Loss - Congestion 2019-11-27 Production Loss -
MW congestion
MW congestion
extending the wall up over the escalator
Restricted Movement
Made with FlippingBook - professional solution for displaying marketing and sales documents online