REA Final - 22 Dec 20 - eBook - 1682 pages
Spearhead Field Notes - PBB
Date
Issue
Field Note
Additional Notes
2019-11-03 Production Loss - SWJV - No Schedule
3rd floor mechanical room 3-hour wall.
6 guys struggling to get installed ahead of tin knocker (2 days); just happened to hear about it; tin knocker nice enough to mention; so gary decided to work Sunday after telling everyone they wouldn't be there on sun and then 4 guys for 6 days returned 4 times, material wasn't loaded; plus all inspections 3: built an 8' header so we could finish top and continue to load job (tin knocker needed to bring in a fan and materials); could not close up, 5th time coming back for 8' by 10' opening for garbage removal and all trades materials
2019-11-03 Production Loss - SWJV - No Schedule 2019-11-03 Production Loss - SWJV - No Schedule
building 3-hour wall on mechanical floor
building 3-hour wall on mechanical floor
2019-11-05 Production Loss - SWJV - No Schedule
sister slab that they didn't pour so we had to leave out the shaftwall
finished top so they could pour; had to run a post
2019-11-05 Production Loss -
this is the second floor elevator shaft reacts them to pull these little pads so we could control shampoo and they never did it so we installed the shampooer and everything else they don't get their stuff done then we get ours nothing else right that's ri
spoke about this earlier
Restricted Movement
2019-11-06 Damage - by Others 2020-02-14 Comeback - Waiting on Others 2020-01-11 Comeback - Waiting on Others 2019-11-06 Production Loss - Equipment "down"
rapid Deco board is about 10 pieces that damaged
damage by lull; hit edge of dumptster 10 pieces; had to reload
tape ceilings
Right hand side of the Q9 soffit framing getting finished
CONGESTION!
will probably 80% done with a delivery and they stopped to artillery in are bringing down somebody else's machine so waiting for the crane to get the last two piles of sheetrock up
had 2 piles to go but stopped because SWJV wanted to use crane to bring anvil machines down; nobody was there to take them; stopped our delivery, took 2 hrs to get down, sat in parking lot but we could have finished our delivery, didn't pick up until the next day right in the middle of our delivery; couldn't wait 30 mins; thought we had too much rock delay getting materials to bring up crates; missing pieces of jigsaw puzzle, delayed our work; could not finish capital without all pieces 100% loss
2019-12-19 Production Loss - SWJV - No Schedule
we're getting more crates of the FRG its 1:30 Thursday in the afternoon
2019-11-11 Delay - by SWJV
Assistant PM continues to find reasons to delay approval
Assistant PM drags his feet w pay approvals
2019-11-12 Progress Brian carr is in orientation starting today. 2020-01-24 Production Loss - SWJV Leroy Luke Craig Thomas and Stephen Joseph sheetrock in the ceiling at the diner, Andre Lewis Jamal and Phil bertrand sheetrock in the wall loading dock
FINALLY SHEETROCKING; WAITED 6 DAYS TO ROCK CEILING