REA Final - 22 Dec 20 - eBook - 1682 pages
Spearhead Field Notes - PBB
Date
Issue
Field Note
Additional Notes
2019-10-27 Production Loss - Weather
we're calling it quits at 1 today due to inclement weather
2020-02-09 Comeback - Waiting on Others 2020-02-12 Comeback - Waiting on Others 2020-02-17 Comeback - Waiting on Others
there are no trim rings on the lights and we're starting to tape the ceiling South end near head house 3rd coat at diner complete. Should be done by tomorrow. WALLS
18 lights w/o tim rings and already have 2 coats; 1 taper had to come back to hit 18 lights 2 times (2 days total) 4 times coming back to add control joints 3 times; soffit obstruction could have finished this in 1 shot… now we have to come back, reload materials, get a machine, send 2 guys to install… 5mins turned into 3 hours… Flowbar had to be cut open; should have been installed w framing; which we would sheetrock into. Flowbar needed before rock. Had to cut back sheetrock to allow for flow bar; no locations given for start and stops; also had to add framing to account for gaps where there were not flow bars; 2 guys 1 week; cut back, then frame "patch" then rock (tape already accounted for) from 8 feb to 15 feb (7 days) we waited to close ceiling; had a day crew and night crew waiting for lights not installed (lost and found), inspections, sprknklers needed to be set, siesmic for other trades)= 6*7*8=336 hours we waited/lost: not productive and even more congestion was a loss of 20%... on hold...
duct pipe needs to be insulated so we could finish sheetrock in the ceiling in front of the elevator
2020-02-12 Comeback - Waiting on Others
Flowbar had to be cut open; should have been installed w framing; which we would sheetrock into. Flowbar needed before rock. Had to cut back sheetrock to allow for flow bar; no locations given for start and stops;
2020-02-15 Comeback - Waiting on Others
ALL LIGHTS
2019-10-30 Production Loss - Congestion
very congested conditions on the 4th floor
2020-02-12 Comeback - Waiting on Others
Need illuminated sign to be installed. Cannot close without this.
have to reload materials and install (2 guys, 2 hours), 1 taper to comeback (1 hr)+(5% inefficient)
2019-11-01 Production Loss - SWJV we worked overtime to deliver to the second floor! me, Mike Rizzo , Thomas O'Reilly 2019-12-16 Comeback - Waiting on Others finish bottom part that was exposed 2019-11-03 Damage - by Others this is the 4th floor elevator shaft l board got removed to weld steel or wood steel in. access fireproofing on the trusses
Made with FlippingBook - professional solution for displaying marketing and sales documents online