2019-10-12 Progress 2019-10-12 Progress

progress on the shaftwall

the fireproofing was already scraped off this being so we're going to shoot our z channel to where it's scraped off already starting insulation on the shelf pool at the elevator on the third floor we had a couple of deliveries today,Von Rohr, Kamco to HH side and to PBB side.Materials for the 4th floor and the 3rd floor FRG is being loaded to the 4th floor [Contract schedule shows GFRG/C installation May - October 19 for total of 8 possible months vs 3 months allotted) col 7 + 6 they're out of plumb 2in plus they have excess monokote on them, have two notch our framing to fit we are loading both sides of the third floor [still no exterior wall framing by Cord] what continue to frame the columns on the 4th floor we can't do the Westside over the roadway there's no glass in very windy today

no backcharge

2019-10-14 Progress 2019-10-17 Progress

2019-10-18 Production Loss - SWJV - No Schedule

3 month delay

2019-10-18 Progress

2019-10-19 Production Loss - SWJV - Steel 2019-10-19 Production Loss - SWJV - No Schedule 2019-10-19 Production Loss - Waiting on Others

image of framing out of plumb; already accounted for above

DAY 7 - Cord

Day 1 - CurtainWall - held up work because bridge not enclosed by curtain wall over active roadway. Then, we had issue accessing the trusses because we couldn't use boom 12 clips and 1 stud at 4 hrs each leg; 2 legs - took 3 days, should haver taekn 1 day, 2 days lost loss of productivity off boom; coreboarding, dangerous (side of escalator wall), then sheetrock on inside of escalator

2019-10-19 Production Loss -

Mike Rizzo and Hector what kind of shaft wall of the triangle from the outside [Unproductive Work; Cannot access from interior w lifts; Have to build Shaftwall from Boom on exterior]

Restricted Movement

2019-10-19 Progress

3 hour wall

2019-10-19 Production Loss -

started doing the 3-hour shaftwall on the slope of the escalator

4 guys struggling to get 3hr wall built

Restricted Movement

2019-10-19 Progress we received six crates are at FRG 2019-10-19 Production Loss - SWJV loading sheetrock to the third floor

extremely difficult delivery w safety steeps and shakeout