REA Final - 22 Dec 20 - eBook - 1682 pages
Spearhead Field Notes - PBB
Date
Issue
Field Note
Additional Notes
2019-10-12 Progress 2019-10-12 Progress
progress on the shaftwall
the fireproofing was already scraped off this being so we're going to shoot our z channel to where it's scraped off already starting insulation on the shelf pool at the elevator on the third floor we had a couple of deliveries today,Von Rohr, Kamco to HH side and to PBB side.Materials for the 4th floor and the 3rd floor FRG is being loaded to the 4th floor [Contract schedule shows GFRG/C installation May - October 19 for total of 8 possible months vs 3 months allotted) col 7 + 6 they're out of plumb 2in plus they have excess monokote on them, have two notch our framing to fit we are loading both sides of the third floor [still no exterior wall framing by Cord] what continue to frame the columns on the 4th floor we can't do the Westside over the roadway there's no glass in very windy today
no backcharge
2019-10-14 Progress 2019-10-17 Progress
2019-10-18 Production Loss - SWJV - No Schedule
3 month delay
2019-10-18 Progress
2019-10-19 Production Loss - SWJV - Steel 2019-10-19 Production Loss - SWJV - No Schedule 2019-10-19 Production Loss - Waiting on Others
image of framing out of plumb; already accounted for above
DAY 7 - Cord
Day 1 - CurtainWall - held up work because bridge not enclosed by curtain wall over active roadway. Then, we had issue accessing the trusses because we couldn't use boom 12 clips and 1 stud at 4 hrs each leg; 2 legs - took 3 days, should haver taekn 1 day, 2 days lost loss of productivity off boom; coreboarding, dangerous (side of escalator wall), then sheetrock on inside of escalator
2019-10-19 Production Loss -
Mike Rizzo and Hector what kind of shaft wall of the triangle from the outside [Unproductive Work; Cannot access from interior w lifts; Have to build Shaftwall from Boom on exterior]
Restricted Movement
2019-10-19 Progress
3 hour wall
2019-10-19 Production Loss -
started doing the 3-hour shaftwall on the slope of the escalator
4 guys struggling to get 3hr wall built
Restricted Movement
2019-10-19 Progress we received six crates are at FRG 2019-10-19 Production Loss - SWJV loading sheetrock to the third floor
extremely difficult delivery w safety steeps and shakeout
Made with FlippingBook - professional solution for displaying marketing and sales documents online