REA Final - 22 Dec 20 - eBook - 1682 pages

Spearhead Field Notes - PBB

Date

Issue

Field Note

Additional Notes

2019-10-03 Production Loss - Rework 2019-10-04 "Real Prick"

the toe kick at the columns trusses didn't allow for the fireproofing on the trusses, Spearhead did not scrape any off Follow up email memorializing serious conversation on Tues, 2 Oct 19, about PM's threat to SpCx. Follow up email memorializing serious conversation on Tues, 1 Oct 19, about PM's threat to SpCx. one of the scissor list wasn't working yesterday Sunbelt is here today fixing it black iron on the fourth floor was damaged from fireproofer

this should be a swjv backcharge; delay to start our work while we waited to install each base (fireproof inspction)

2019-10-04 "Real Prick"

2019-10-04 Production Loss - Weather 2019-10-04 Damage - by Others

challenge to get up there, lines re-snapped, congestion, hoses in the way waited 4 hours each pic should only take 30 mins; should have taken 1 hr to load

2019-10-05 Production Loss - SWJV it's 20 after 12 we got all the stuff up to 4 we're going to take lunch and then we're going to bring all the stuff to the other end by the elevator 2019-10-05 Production Loss - SWJV our delivery was here at 8 Atlantic is using a magnet first they are still using it it's quarter to ten so we haven't got our material up yet

another trade hopped in front of us, added cost for kamco wait time for delivery; 2x ready to offload; loss of productivity

2019-10-05 Delay - by SWJV

roughly 10 I believe this is the last pick and we should be starting our delivery

2019-10-05 Progress 2019-10-05 progress

sheetrock on the 4th floor

We are continuing to work on the trusses on the first floor and sheetrocking electric room

2019-10-07 progress

Panelmax Delivery amd progress im Elevator

build shanty; plus set up, training for nick and other JM additional layout, levels 2 and 3 (4th floor already accounted for)

2019-10-09 Production Loss - SWJV - Steel

we were directed not to follow the access line and follow the steel around the elevator. it's roughly an inch out off from the access line .

2019-10-11 Progress

We are continuing to do black iron on the 4th floor getting the clips ready for the framing on the 4th floor and also getting ready for the shaft wall we plan on doing tomorrow on the third floor core board started going in [No Exterior Framing Installed by Cord]

2019-10-12 Production Loss - SWJV - No Schedule 2019-10-12 Production Loss - SWJV - No Schedule

DAY 1 - Cord

red pipes going in fourth floor [MEP should have already been in - dates May to August 19]

SCHEDULE- we coulndt access the area, had to hook pencil rod asfter red pipes when in, and rrideg across avove the red pipes in order to hang black iron; math 3 days per guy for extra bridgeing and hanging pipes: extra bridging 5 days to hang rod) was 1 entire week per guy

2019-10-12 Progress

beginning to frame the elevator shafts yeah yeah yeah

Made with FlippingBook - professional solution for displaying marketing and sales documents online