Meeting #12

case-by-case basis if needed during construction

Previous Meeting Minutes: 5/28/2019 - SWJV meeting with Island on 5/29/19; will set up meeting with Spearhead and Island in potentially 2 weeks; SWJV and Spearhead to look further into bolt connections with SOFP to see if RFI for general condition allowing < 2” at these locations is acceptable in case Spearhead needs to scrape some off in the tight areas UPDATE 5/29/19 per meeting with Island: hanger depth is 6" from surface; so if attached to deck 6" from deck, if to steel 6" from BOS 5/14/2019 - Setup Meeting First week of June. Need to discuss hanger depth, 6” from bottom of steel or bottom of deck. 4/29/2019 – SWJV to verify hanger depth from bottom of steel or deck. 4/9/2019 - SWJV is targeting SOFP middle of June start date. Field coordination meeting prior to starting clips. See 4/2/2019 Meeting Minutes for Previous Notes