Meeting #12

Coordination: Deliverables/Equipment/Logistics

No

Meeting Origin Title

Assignment

Due Date Priority Status Old/New?

4.1

1

GRFG Substitution Mockup Sean Reed (Spearhead)

2/28/2019 High Open Old

Description: Brian to send substitution email for LGP confirmation this week; HOK accepted the official drawing confirming each item that is gyp in lieu of GFRG per RFI

Previous Meeting Minutes: 5/28/2019 - Brian to send substitution email for LGP confirmation this week; Spearhead to submit official drawing as requested by HOK confirming each item that is gyp in lieu of GFRG 5/14/2019 - SWJV to send substitution confirmation from LGP. 4/29/2019 – Informal approval from LGP. SWJV to get confirmation. 4/9/2019 - Reviewed with LGP. Spearhead to submit follow up RFI regarding control joints between GRG and GFRC. 4/2/2019 – Mockup complete, Reviewing with LGP 4/9/2019 3/26/2019 - Spearhead will spackle and paint existing mockup. Mockup is located in Mockup room, see Zack Trause for access. 3/19/2019 - Mockup review with LGP was positive. LGP requested to see final finish on mockup. Spearhead will send finishers to perform work week of 3/25/19. Mockup has been relocated to LGP mockup room, please contact Zack Trause for access. See 4/2/2019 Meeting Minutes for Previous Notes

4.2

1

Radiator Enclosure Mockup Doug Moore (SWJV)

3/15/2019 High Open Old

Description: Celtic confirmed Thursday, 6/20

Previous Meeting Minutes: 5/28/2019 - Celtic to advise date 5/21/2019 – Met with Doug from SWJV to discuss details, reference Coordination Matrix. Forthcoming info coming from Celtic. 5/14/2019 - Meeting scheduled with Celtic to work out details 4/29/2019 – Setting up meeting for week of 5/13/2019 4/9/2019 - Preliminary Shop Drawings received from Celtic. SWJV will send to Spearhead for review/comment. 4/2/2019 – Celtic producing preliminary drawings for review and comment by SWJV See 4/2/2019 Meeting Minutes for Previous Notes

4.3

1

Site Requirements - Conex SWJV

3/5/2019 Medium Open Old

Description: No updates

Previous Meeting Minutes: 5/28/2019 - current Spearhead conex box will not be moving, no additional charges if not hooking up; SWJV provided cost for hookup if Spearhead looking to get another box with electricity; if more conex boxes become available, SWJV to notify Spearhead 5/14/2019 - Cost meeting upcoming, will request information on hookup costs . 4/29/2019 – SWJV to check on revised costs for hookups. 4/9/2019 - Re-Opened. Spearhead to look into using second box which could potential receive power. SWJV to send hookup cost. 4/2/2019 - CLOSED . See 4/2/2019 Meeting Minutes for Previous Notes

4.4

2

Deliveries

SWJV/Spearhead

Ongoing Low Open Old

Description: Demo team to reschedule DMS training for Sean Reed.

Previous Meeting Minutes: 5/28/2019 - Sean Reed participating in DMS training for Demo team

4/2/2019 – Discussed site logistics for deliveries See 4/2/2019 Meeting Minutes for Previous Notes

4.7

3

Fireproofing Coordination

Gary Miuccio (Spearhead)

3/22/2019 Low Open Old

Description: meeting with Island and other subcontractors (including Spearhead) took place prior to this meeting on 6/12; Gary to install a couple angles on PBB steel slanted columns as a “mockup” for Island to review SOFP condition; Murat to send Spearhead the HH submittal for top track used in HH interior walls; SWJV to review SOFP thickness requirement at bolts but plan is to submit RFI as