Meeting #10

Coordination: Deliverables/Equipment/Logistics No Meeting Origin Title

Assignment

Due Date Priority Status Old/New?

4.1

1

GRFG Substitution Mockup Sean Reed (Spearhead)

2/28/2019 High Open Old

Description: SWJV to send substitution confirmation from LGP.

Previous Meeting Minutes: 4/29/2019 – Informal approval from LGP. SWJV to get confirmation. 4/9/2019 - Reviewed with LGP. Spearhead to submit follow up RFI regarding control joints between GRG and GFRC. 4/2/2019 – Mockup complete, Reviewing with LGP 4/9/2019 3/26/2019 - Spearhead will spackle and paint existing mockup. Mockup is located in Mockup room, see Zack Trause for access. 3/19/2019 - Mockup review with LGP was positive. LGP requested to see final finish on mockup. Spearhead will send finishers to perform work week of 3/25/19. Mockup has been relocated to LGP mockup room, please contact Zack Trause for access. 3/12/2019 - SWJV to get additional information/mockup requirements from LGP. No formal substitution request needed for DJV. See 4/2/2019 Meeting Minutes for Previous Notes

4.2

1

Radiator Enclosure Mockup Doug Moore (SWJV)

3/15/2019 High Open Old

Description: Meeting scheduled with Celtic to work out details

Previous Meeting Minutes: 4/29/2019 – Setting up meeting for week of 5/13/2019 4/9/2019 - Preliminary Shop Drawings received from Celtic. SWJV will send to Spearhead for review/comment. 4/2/2019 – Celtic producing preliminary drawings for review and comment by SWJV 3/26/2019 - SWJV has meeting with Celtic on Wednesday at 7:30am. SWJV/Celtic/Spearhead to coordinate seam, material thickness and attachment to radiator enclosure.

3/19/2019 - SWJV will work with Celtic to provide information. 3/12/2019 - SWJV to reach out to Celtic regarding status. See 4/2/2019 Meeting Minutes for Previous Notes

4.3

1

Site Requirements - Conex SWJV

3/5/2019 Medium Open Old

Description: Cost meeting upcoming, will request information on hookup costs .

Previous Meeting Minutes: 4/29/2019 – SWJV to check on revised costs for hookups. 4/9/2019 - Re-Opened. Spearhead to look into using second box which could potential receive power. SWJV to send hookup cost. 4/2/2019 - CLOSED 3/26/2019 - Locks have been swapped. There may be a potential move to accommodate site logistics. SWJV to send logistics for employee site access based on 102 nd street work. 3/19/2019 - Rental form signed and sent to cost and logistics team. 3/12/2019 - Sean Hickey working on locations available with SWJV Logistics team. Rental information and Cost may be revised by SWJV Logistics/Cost Team. SWJV to forward revised information when available. See 4/2/2019 Meeting Minutes for Previous Notes

4.4

2

Deliveries

SWJV/Spearhead

Ongoing Low Open Old

Description: Ongoing Previous Meeting Minutes:

4/2/2019 – Discussed site logistics for deliveries See 4/2/2019 Meeting Minutes for Previous Notes

4.7

3

Fireproofing Coordination

Gary Miuccio (Spearhead)

3/22/2019 Low Open Old

Description: Setup Meeting First week of June