Meeting #10

Previous Meeting Minutes: 4/29/2019 – SWJV to verify hanger depth from bottom of steel or deck. 4/9/2019 - SWJV is targeting SOFP middle of June start date. Field coordination meeting prior to starting clips. 3/26/2019 - SWJV to verify if 6” hanger requirement is below deck or below Bottom of Steel. 3/19/2019 - Ongoing

3/12/2019 - SOFP contractor requested that attachments or hanging rods not extend 6” to maintain access and safe working space for spray on fireproofing. Spearhead to let SWJV know if they would like to set up coordination in field with SOFP Superintendent. See 4/2/2019 Meeting Minutes for Previous Notes