Previous Meeting Minutes: 4/29/2019 - Setting up meeting for 6/13 to coordinate with Celtic, Anvil, Kone, 580/Kone. 4/2/2019 – Send smoke curtain shop drawings for Spearhead information. Framing for smoke curtain by others . 3/19/2019 - SWJV MEP team will reach out to subcontractors to see if they are providing own unistrut for conduit and piping. SWJV to provide lighting layout and any low voltage submittals for coordination. 3/12/2019 - SWJV sent Spearhead cut sheets for the light fixtures, and layout contract drawings for coordination with GFRC bases. SWJV to advise if working off of contract documents or provide subcontractor layout shop drawings. See 4/2/2019 Meeting Minutes for Previous Notes