Division 01 - DDC STANDARDGENERAL CONDITIONS SINGLE CONTRACT PROJECTS Issue Date - June 01, 2013 Revised - January 15, 2015
-3,_,.,,.=,-•
.. DESIGN + CONSTRUCTION
8. Design Consultant: "Design Consultant" shall mean the entity responsible for providing design services for the Project, including without limitation, preparing the construction documents (drawings and specifications) and providing services in connection with such documents during construction. The entity serving as the "Design Consultant" may be a corporation, firm, partnership, joint venture, individual or combination thereof. Such entity may be either an employee(s) of the City or an entity engaged by the City to provide such services. C. Commissioner: The Commissioner of the Department of Design and Construction of the City of New York, his/her successors, or duly authorized representative(s). D. BoD: Basis of Design: A document, prepared by the Consultant Architect/Engineer, that records concepts, calculations, decisions, and product selections used to meet the OPR and to satisfy applicable regulatory requirements, sta,ndards,and guidelines. The document includes both narrative descriptions and lists of individual items that support the design process. E. Commissioning Plan: A document that outlines the organization, schedule, allocation of resources, and documentation requirements of the commissioning process.
F. CxA: CommissioningAgent (Aka CommissioningAuthority) under separate contract with the City of New York to provide Commissioning Services for this project.
G. OPR: Owner's (City of New York) Project Requirements: A document, prepared by the Consulting Architect/Engineer) that details the functional requirements of a project and the expectations of how it will be used and operated. These include Project goals, measurable performance criteria, cost considerations, benchmarks, success criteria, and supporting information.
H. Systems, Subsystems, Equipment, and Components: Where these terms are used together or separately, they shall mean "as-built" systems, subsystems, equipment, and components.
I.
TAB: Testing, Adjusting, and Balancing.
1.5 COMMISSIONINGTEAM: A.
Members Appointed by the Contractor and its Subcontractors: Individuals, each having authority to act on behalf of the entity he or she represents, explicitly organized to implement the commissioning process through coordinated actions. The commissioning team shall consist of, but not be limited to, representatives of the Contractor, including Project superintendent and subcontractors, installers, suppliers, and specialists deemed appropriate by the CxA. B. Members Appointed by the City: 1. CommissioningAuthority/Agent (CxA): The designated person, company, or entity under separate contract with the City that plans, schedules, and coordinates the commissioning team to implement the commissioning process. 2. Representativesof the facility user and operation and maintenance personnel. 3. Consultant Architect/Engineer and other concerned entities.
1.6 CITY'S RESPONSIBILITIES: A.
Provide the OPR documentation to the Commissioning Agent (CxA) for use in developing the commissioning plan; systems manual; operation and maintenance training plan; and testing plans and checklists. B. Assign operation and maintenance personnel and schedule them to participate in commissioning team activities.
GENERAL COMMISSIONING REQUIREMENTS 019113-2