REA Final - 22 Dec 20 - eBook - 1682 pages

Spearhead Field Notes - PBB

Date

Issue

Field Note

Additional Notes

2019-09-18 Production Loss - SWJV it's 2:26 and we have two more trips to go up 2019-09-18 Production Loss - SWJV last load going up now 243 2019-09-18 Production Loss - SWJV material was dropped off early this morning we were told we were getting the magni at 1 to lift it up it's now 1:23 and there's no Magni still

delay getting materials

2019-09-19 Damage - by Others

I spoke with Frank from skanska about are black iron that was damaged and he said that he will pay for the black iron to get replaced if it if it was a small amount , I told him it was roughly six to eight hours of work , he said we'll make it up when we work overtime and he doesn't want to make a big deal of it we started to frame columns they have almost four and a half inch of fireproofing on some of these columns [Captured on separate CO] we're finishing up the Spackle in the electric room has to just polish it tomorrow Friday he'll be done the fire sprayer has about four and a half inch of Monaco Donna [monocoat] beam I showed Frank Carrillo today and it's a lot of extra work to chip that stuff out so they either have to go ahead of us and scrape it where is heavy or pay us to do it [captured separately]

2019-09-19 Production Loss - Rework

verify covered previously

2019-09-19 Progress

2019-09-20 Production Loss - Rework

2019-09-20 Progress

they are starting to install the stairs on first floor

2019-09-26 Production Loss -

spearhead stayed 4 hours overtime today to make use of the boom there was me and for [4] guys

20hrs overtime to use boom

Restricted Movement

2019-09-26 Production Loss -

we got top track up for the wall along the escalator did the first section framing at escalator day 1 ; without poured floor , we could have been far more productive; poor planning

Restricted Movement

2019-09-27 Production Loss - SWJV - Steel

they moved the access line on the fourth floor boo [Col B00] looks like about 1 in We are continuing to do some layout on the 4th floor frame trusses on 4th floor we're also framing on the third floor by the elevator escalator and insulating on the third floor

mock arquues the line is in the same spot; but it's not; had to re-layout

2019-09-27 Progress

Made with FlippingBook - professional solution for displaying marketing and sales documents online