REA Final - 22 Dec 20 - eBook - 1682 pages

Spearhead Field Notes - PBB

Date

Issue

Field Note

Additional Notes

2019-08-26 Production Loss - SWJV - Steel 2019-08-26 Production Loss - Equipment "down"

Brian Mock called re: 3d scanning of the bridge. they will be able to get us work points mid week to be able to set our ceiling heights.

Day 5 - Access/Control Pts/Elevations

Loss of Production

lost time due to comeback time to complete task unavailable due to no lift

2019-08-26 Production Loss - Rework

just still spraying on the third floor soon as they're done, they're going to bring the our lift up Monday the 26th

no framing due to no lift; no clips in, had to scrape top track; had to scrape some of the columns for bracing to add framing; nobody had a chance to get there after the concrete and then the spray; fproofer went to 3 because 4 wasn't ready for him; was laid out but got covereed; we could not get our lift up; have an impact on framing production and we have to re layout walls covered with spray

2019-08-26 Production Loss - Congestion

Hilti came today to demonstrate to lasers a red beam and a green bean to see which one's the best for us to use the red beam has the ability to do slopes. it's very crowded on the 4th floor all the trades everyone's working together but it tough to move around skanska has to resnap their access lines on the third floor was covered over with fire spray . it's Tuesday the 27th the list [lift] still on the ground the finishing that has five Spraying and then they're going to bring out lift up. you need to get the garbage cleaned up so we could lay out is rebar up here guy needs to get put on top of the pad We are continuing to do black iron and then stalling [installing] hangers to the black iron we also are installing the clips for the trusses. we did some layout on the third floor today. they are finishing up the fireproofing and cleaning up the rest of the fireproofing off the floor and excess materials so we could bring our lift and start framing the electric room that's skanska asked us to do we [are] still waiting for some access lines to get back on the third floor that were covered with the fireproofing would like to double- check all marks to make sure good they brought our scissor lift up to the third floor Monday afternoon so we're able to start shooting some top track today on the third floor.

2019-08-27 Production Loss - SWJV - Steel 2019-08-27 Production Loss - Equipment "down"

had to re-layout walls and double check llines that you could barely see loss time 2hrs 2 guys lost time due to comeback time to complete task unavailable due to no lift

2019-08-27 Production Loss - Rework

still havent taken garbarage off 3rd floor; nobody moved rebor, so we put rebar on top of pads so we could start to shoo top track

2019-08-28 Production Loss - SWJV - Steel

Day 5 - Access/Control Pts/Elevations

2019-08-28 Production Loss - Equipment "down"