Spearhead Field Notes - PBB
Date
Issue
Field Note
Additional Notes
2019-08-22 Production Loss - Equipment "down"
The benchmark on pedestrian bridge b headhouse side was changed it's a half inch lower and the original 81 foot benchmark. are scissor lift is still has not been brought to the 3rd floor also we're going to need the materials to build the electric closet on the third floor. the spearhead is still waiting for an elevation so we could set our black iron. on the 4th floor bridge b. they still have to clean off of the third floor they're taking the very off and has also rebar that's laying on the floor needs to be moved to a location so we could drive the left and build the electric room. The benchmark on pedestrian bridge b headhouse side was changed it's a half inch lower and the original 81 foot benchmark. are scissor lift is still has not been brought to the 3rd floor also we're going to need the materials to build the electric closet on the third floor. the spearhead is still waiting for an elevation so we could set our black iron. on the 4th floor bridge b. they still have to clean off of the third floor they're taking the very off and has also rebar that's laying on the floor needs to be moved to a location so we could drive the left and build the electric room. this is picture of The benchmark that was lowered
lost time due to comeback time to complete task unavailable due to no lift
2019-08-22 Production Loss - SWJV spearhead construction is having a hard time charging are left [our lifts] and charging are [our] batteries there's not enough power up there on the bridge so we need to address it
had to get extension cords to try to charge while in use; hopping from socket to socket, hopping around trying to get power and running cords/ resetting breakers - wait time for electrician to flip switch comeback work; we had started layout, had to leave for concrete pour into forms, lines covered, had to do re-work, then rebar was in way and we had to comeback to finish, area wasn’t available to us; comeback to finish time (set up) + re-work of what got covered + initial reassignment to new location; see white and yellowmarks on floor
2019-08-22 Comeback - Waiting on Others
2019-08-22 Production Loss - SWJV - Steel 2019-08-23 Production Loss - Equipment "down"
Day 4 - Access/Control Pts/Elevations; adjusted new elevation at B5 which we then followed the raike of the curtain wall from that point
I'll [Our] lift is still on the ground it's Friday August 23rd roughly 3:00 lost time due to comeback time to complete task unavailable due to no lift
2019-08-23 Progress
good good news we have power now up on 4 so we can plug out lifts in and our battery chargers