LaGuardia CTB Replacement Project Pedestrian Bridge B – Additional Interior Framing Items Meeting Minutes ______________________________________________________________________________________ c. Elevator Shaft Walls Spearhead will frame elevator after weld signoff, anticipated start 10/12/19 d. Stair Walls SWJV to confirm start date. Approx. 1 week until stair complete on L3 4. 2 nd Floor Items a. Pet relief, Janitor Closet, Storage – Spearhead will load after SWJV elevator welding complete and floor cleaned b. Elevator Shaft and Stairs – Spearhead will load after SWJV elevator welding complete and floor cleaned. Stairs complete

Page 3

Pedestrian Bridge B – Additional Interior Framing Items