REA Final - 22 Dec 20 - eBook - 1682 pages
Schedule
Impact of no schedule
HH Plasterform Order
Bridge Delivery not Guaranteed SpCx truss leg fabrication (2 Carps, not included in bid price)
No Schedule
Leads to poor coordination SpCx improvised w color-coded Heat Map Superintendents agreed with SpCx plan Work East to West Moving Walkway (MW) first Escalator West Wall Relied on Pull Meeting notes Became Wild West
Out of Sequence Work Cannot Start at MW
Major loss of productivity
All Plasterform pieces sequenced for MW came out of order Had to work 2nd shift due to MW installation Could not start at MW pit; had to use Booms 70 feet off ground to add clips
Obstacles
Example: Glass handrails installed prior to installing GFRC bases
Comebacks
Example: Ceiling in Diner 4x Damage to black iron, constant (including “wind”)