Steel
Impact of Steel
Bridge "dropped" Concrete added to elevate FF Roof "dipped"
Changed ceiling elevations (Example: 3x @ North) GFRG Soffit flares would not line up w/o substantial modification
Fabricate Gyp Soffit Flares - unexpected Access lines no longer centered on trusses Required constant verification Major loss of productivity Clips field modified Framing field modified GFRG/C pieces field modified Required vigilance to hold correct line Could not add "just anybody" for installation Plasterform quoted additional $70k SpCx had to absorb modification costs in the field
Out of plumb
Bolts backwards