REA Final - 22 Dec 20 - eBook - 1682 pages
Meeting #13
Project Schedule
No
Meeting Origin Title
Assignment
Due Date Priority
Status
Old/New?
5.1
1
Preliminary Schedule Review Brian Mock (SWJV)
3/31/2019 Medium Open
Old
Description: SWJV to confirm roofer start date to ensure Spearhead can install BBHs before (assuming approved by HOK); Tentatively have a Scheduling Pull Plan Meeting with subcontractors on 7/17-18 Previous Meeting Minutes: 6/12/2019 - SWJV provided 6 week look-ahead with Spearhead; Spearhead submitted revised schedule pushing out to end of Feb 2020 – will need acceleration 5/28/2019 - KONE does not need glass handrails for moving walkway during main install; SWJV to meet with KONE within the next week to provide further information to Spearhead, mostly with work above escalators and coordination with platforms and rigging 5/14/2019 - Need to coordinate interior framing and finishes with moving walk ways and elevator. Will work with Kone to provide information. Look into installation sequencing and alternatives such as leaving out glass handrail. Updated milestone dates to be provided by SJWV indicating start and completion date. Based on schedule will need to evaluate if night work is required. If second shift work is required costs will be discussed. Preliminary schedule provided for Platerform fabrication. 4/29/2019 – SWJV to get schedules for VT and MEP 4/9/2019 - Spearhead to update information when information becomes available regarding Plasterform/Corinthian scope. SWJV to
provide information from Kone regarding installation. See 4/2/2019 Meeting Minutes for Previous Notes
5.3
1
Spearhead Start Date
Brian Mock (SWJV)
2/28/2019 Medium Open
Old
Description: No changes
Previous Meeting Minutes: 5/28/2019 - July start date; scheduling Spearhead to start on roof for blue bangers once deck and perimeter protection is down 5/14/2019 - SWJV now anticipating July Start date. Concrete pour scheduled for middle of June. 4/9/2019 - SWJV anticipating June start date See 4/2/2019 Meeting Minutes for Previous Notes
5.4
10
Trade Schedules
Brian Mock (SWJV)
6/15/2019 Medium
Open
Old
Description: SWJV to review scaffold above escalator with Safway and KONE for confirmation
Previous Meeting Minutes: 6/12/2019 - SWJV to review scaffold above escalator with Safway 5/28/2019 - SWJV to provide schedules for KONE and Island; ZT and SR/GM reviewed CB overhead door by McKeon for coordination 5/14/2019 - Schedules for Celtic, Anvil, Kone, and Island FP needed for coordination
6
Made with FlippingBook - professional solution for displaying marketing and sales documents online