Division 01 -DDC STANDARD GENERAL CONDITIONS SINGLE CONTRACT PROJECTS Issue Date June 01, 2013 Revised - January 15, 2015
~~-=•~~ DESIGN + CONSTRUCTION
4. Scope of Drawings: Shop Drawings shall be numbered consecutively and shall accurately and distinctly represent all aspects of the work, includingwithout limitation the following: a. All working and erection dimensions b. Arrangements and sectional views c. Necessary details, including performance characteristics, and complete information for making necessaryconnections with other work d. Kinds of materials including thickness and finishes e. Identificationof products f. Fabricationand installation drawings g. Roughing-inand setting diagrams h. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring i. Shop work manufacturing instructions j. Templates and patterns k. Schedules I. Design calculations m. Compliancewith specified standards n. Notationof coordination requirements o. Notationof dimensions established by field measurement p. Relationshipto adjoining construction clearly indicated q. Seal and signature of professional engineer if specified r. Wiring Diagrams: Differentiatebetween manufacturer-installedand field-installed wiring s. All other information necessary for the work and/or required by the Commissioner 5. Titles and Reference: Shop Drawings shall be dated and contain: a. Name of the Project, DDC Project Number and Contract Number b. The descriptive names of equipment, or materials covered by the Contract Drawings and the classified item number or numbers, if any, under which it is, or they are required c. The locations or points and sequence at which materials, or equipment, are to be installed in the work d. Cross references to the section number, detail number and paragraph number of the Contract Specifications e. Cross references to the sheet number, detail number, etc., of the Contract Drawings 6. Field Measurements: In addition to the above requirements, the Shop Drawings shall be signed by the Contractor and, if applicable, the subcontractor responsible for preparation of the Shop Drawings. Each Shop Drawing shall be stamped with the following wording: FIELD MEASUREMENTS: The Contractor certifies that it has verified and supplemented the Contract Drawings by taking all required field measurements, which said measurements correctly reflect all field conditions and that this Shop Drawing incorporates said measurements. 7. Contractor's Statement with Submittal: Any Submittal by the Contractor for acceptance, including without limitation, all dimensional drawings of equipment, blueprints, catalogues, models, samples and other data relative to the equipment, the materials, the work or any part thereof, must be accompanied by a statement that the Submittal has been examined by the Contractor and that everything shown in the Submittal is in accordance with the requirements of the Contract Drawings and Specifications. If there is any discrepancy between what is shown in the Submittal and the requirements of the Contract Drawings and Specifications, the Contractor shall, in its statement, list and clearly describe each such discrepancy.
Acceptance will be given based upon the Contractor's representation that what is shown in the Submittal is in accordance with the requirements of the Contract Drawings and Specifications. If
SUBMITTAL PROCEDURES 01 33 00 - 5
Made with FlippingBook PDF to HTML5