Division 01 - DDC STANDARDGENERAL CONDITIONS SINGLE CONTRACT PROJECTS Issue Date June 01, 2013 Revised - January 15, 2015
DESIGN + CONSTRUCTION
2. Field Office Prints: Retain one set of prints of progress photographs in the field office at Project site, available at all times for reference. Identify photographs same as for those submitted to Commissioner. C. Digital Images: Submit digital images exactly as originally recorded in the digital camera, without alteration, manipulation, editing, or modifications using image-editing software. 1. Date and Time: Include date and time in filename for each image. 2. Field Office Images: Maintain one set of images on CD-ROM in the field office at Project site, available at all times for reference. Identify images same as for those submitted to Commissioner. Before commencement of Contract work at the site, take color photographs of Project site and surrounding properties, including existing structures or items to remain during construction, from different vantage points, as directed by the Resident Engineer. 1. Flag applicable excavation areas and construction limits before taking construction photographs. 2. Take photographs of minimum eight (8) views to show existing conditions adjacent to property before starting the Work. 3. Take applicable photographs of minimum eight (8) views of existing buildings either on or adjoining property to accurately record physical conditions at start of construction. 4. Take additional photographs as required or directed by the Resident Engineer to record settlement or cracking of adjacent structures, pavements, and improvements. B. Demolition Operations: Take photographs as directed by the Resident Engineer of minimum of eight (8) views each before commencement of demolition operations, at mid-point of operations and at completion of operations. C. Pre-Demolition Photographs: Take archival quality color photographs, to include all exterior building facades, of all structures at the Project site designated to be fully demolished or removed in compliance with NYC Building Code requirements. Submit four (4) complete sets of pre-demolition photographs, in the format specified herein, to the Resident Engineer for submission to the Department of Buildings. 3.2 PRE-CONSTRUCTION& PRE-DEMOLITIONPHOTOGRAPHS: A.
3.3 PERIODICCONSTRUCTIONPROGRESS PHOTOGRAPHS: A.
Take photographs of minimum eight (8) views bi-weekly as directed by the Resident Engineer of construction progress for each contract trade. Select vantage points to show status of construction and progress since last photographswere taken.
3.4 SPECIAL PHOTOGRAPHS: A.
The photographer shall take special photographs of subject matter or events as specified in other sections of the Project Specifications from vantage points specified or as otherwise directed by the Resident Engineer. B. Historical Elements:As required in Section 013591, HISTORICTREATMENT PROCEDURES, for Contract work at designated landmark structures or sites the photographer, as specified and required by individual sections of the Contract documents or at the direction of the Commissioner, shall take images of existing elements scheduled to be removed for replacement, repair or replication in quantities as directed, including post-constructionphotographs of completed work as directed by the Commissioner.
PHOTOGRAPHICDOCUMENTATION 01 32 33 - 4