Division 01 - DOC STANDARD GENERAL CONDITION SINGLE CONTRACT PROJECTS

43__=-~ DESIGN + CONSTRUCTION

Issue Date June 01, 2013 Revised - January 15, 2015

SECTION 01 54 11 TEMPORARY ELEVATORS AND HOISTS

PARTI-

GENERAL

1.1 RELATED DOCUMENTS:

A. The following documents apply to all required work for the Project: (1) the Contract Drawings, (2) the Specifications, (3) the General Conditions, (4) the Addendum, and (5) the Contract [City of New York Standard Construction Contract].

1.2 SUMMARY: A.

This section includes the following: 1. Temporary Use, Operation and Maintenance of Elevators during Construction a. For New buildings up to 15 Stories b. For New buildings over 15 Stories c. For Existing Buildings 2. Temporary Construction Hoists and Hoist ways (For Material and Personnel)

1.3 RELATED SECTIONS: include without limitation the following: A. Section 01 10 00 SUMMARY B. Section 01 42 00 REFERENCES C. Section 01 50 00 TEMPORARY FACILITIES AND CONTROLS D. Section 01 54 23 TEMPORARY SCAFFOLDS AND SWING STAGING E. Section 01 77 00 CLOSE OUT PROCEDURES

PART 11- PRODUCTS (Not Used)

PART Ill - EXECUTION

REFER TO THE ADDENDUM FOR THE APPLICABILITY OF SUB-SECTION 3.1

3.1 TEMPORARY USE, OPERATION AND MAINTENANCE OF ELEVATORS DURING CONSTRUCTION FOR NEW BUILDINGS UP TO AND INCLUDING 15 STORIES: A. INSTALLATION: The Contractor shall install, complete, operate, and maintain in good working order, as indicated herein, one (1) selected main elevator for the transport of employees of the Contractor and/or its subcontractors, and representatives of the DOC and other Governmental Agencies having jurisdiction of work at the project. The Contractor shall furnish, install, and maintain such elevator in good working order, including all necessary hoisting ropes, governor cables, traveling conductor cables, operating devices, temporary hand reset target annunciators, temporary signal devices, and all other permanent or temporary parts. The installation, operation and maintenance of the temporary elevator and all equipment and/or parts utilized in connection therewith shall be in accordance with the rules and regulations of all agencies and/or entities having jurisdiction over elevators in temporary use. B. RESPONSIBILITY: The Contractor shall be responsible for any injury to persons or damage to property arising out of the temporary elevator and all equipment and/or parts utilized in connection therewith.

TEMPORARY ELEVATORSAND HOISTS 01 54 11 - 1