SECTION 01 50 00 TEMPORARY FACILITIES, SERVICESAND CONTROLS
PART I- GENERAL
1.1 RELATEDDOCUMENTS: A.
The following documents apply to all required work for the Project: (1) the Contract Drawings, (2) the Specifications, (3) the General Conditions, (4) the Addendum, and (5) the Contract [City of New York Standard Construction Contract].
1.2 SUMMARY: A.
This section includes the following: a. Temporary Water System b. Temporary Sanitary Facilities c. Temporary Electric Power, Temporary Lighting System, And Site Security Lighting d. Temporary Heat e. Dewatering Facilities And Drains f. Temporary Field Office for Contractor g. Resident Engineer's Office h. Material Sheds
i. Temporary Enclosures j. Temporary Partitions k. Temporary Fire Protection I. Work Fence Enclosure m. Rodent and Insect Control n. Plant Pest Control Requirements o. Project Identification Signage p. Security Guards/Fire Guards on Site q. Project Sign and Rendering r. Safety
1.3 RELATEDSECTIONS: include without limitation the following: A. Section 01 10 00 SUMMARY B. Section 014200 REFERENCES C. Section 01 54 11 TEMPORARY ELEVATORS AND HOISTS D. Section 01 54 23 TEMPORARY SCAFFOLDS AND SWING STAGING E. Section 01 77 00 CLOSE OUT PROCEDURES
1.4 DEFINITIONS:
A. Refer to Article 2 of the Contract for definition of terms, words and expressions used in the General Conditions not otherwise defined herein.
B. Permanent Enclosure: As determined by Commissioner, permanent or temporary roofing that is complete, insulated, and weather tight; exterior walls which are insulated and weather tight; and all openings that are closed with permanent construction or substantial temporary closures.
TEMPORARY FACILITIES, SERVICES AND CONTROLS 01 50 00 -1