Message 8: Jan 27 2020 6:52 PM

From: Andee Sent: Monday, January 27, 2020 6:52 PM To: Corallo, Frank

Cc: Sean ; Miritello, Suzanne ; Silverman, Scott ; Taylor, Rick ; Jamison, Damond ; Bilgen, Murat ; Mock, Brian ; Dolan, John ; Sheth, Neha ; Rose Ott Subject: Re: URGENT REQUEST for COR Approval - Spearhead Construction Re: PBB 01/11-01/17 OT

[External Email]

Frank,

Thank you. We are happy to see that Change Order Requests for work performed in November will be available for signature by Jan 28th. Does this mean those Change Orders will be included in January's draw (Draw 101C)? Separately, we submitted the SWAC reimbursement for two reasons. First, Spearhead anticipated a peak labor force of 20 workers based on our contract schedule (Apr-Nov 19). The delayed start compressed our schedule from 8 months to 5 months. As a result, we had to SWAC an additional 26 workers for a total of 46 SWAC applications, which is why we submitted the $12,710 for reimbursement.

Frank, I respectfully request that you reconsider this additional financial burden to Spearhead and approve the Change Order as requested.

Thank you, Frank.

Take care,

-Andee

Andee Hidalgo Owner & President Spearhead Construction, LLC MBE | WBE | SDVOB | SDVOSB | PANYNJ | NYCSBS Andee@SpearheadCx.com Ph: 917.834.3400

The information contained in this email message is legally privileged and confidential information intended solely for the use of the intended recipient(s). If you are not the intended recipient(s), any distribution, dissemination, or reproduction of this email message is strictly prohibited. If you have received this message in error, please immediately reply to the sender and then destroy this message.