Spearhead Impact of Delayed Start
Compressed Work Duration
Spearhead Lost Productivity
Impact of Delayed Start
Compressed Duration
Spearhead Innovation Blue Banger Hangers Panelmax (2 Carps, not included in bid price)
Inefficient Access to work areas
Loss of Productivity; Lost time
Poor Scaffold Design
Spearhead provided efficient scaffold solution; PM’s inefficient scaffold resulted in lost time, 3-tiered bakers on top of scaffold, and pipe scaffold directly on escalator treads
Spiders
Takes 3.5 mins RT to reach location @ Moving Walkway
Congestion
Loss of Productivity Trade stacking; Overmanning GFRG sat in warehouse for entire month due to congestion on bridge Request to work 2nd shift to alleviate congestion (denied)
Lull, 1 ea
Delays in getting materials and equipment to work areas 3 weeks to hoist last Spearhead lift Delays waiting for repairs to lull
Overtime
Consecutive days of overtime leads to substantial lost productivity