Spearhead Key Dates
Substantial Completion: 6 months vs 9 months
Spearhead Substantial Completion
Subcontract Agreement Spearhead Subcontract Agreement
30 Jan 19
Contract Milestone Start Contract Start
Apr 19
Key Milestone Dates Spearhead Start and Substantial Completion
Actual Start Date Official Spearhead start date.
14 Aug 19
BOH CO #2 Spearhead BOH CO #2
30 Aug 19
Contract Milestone End Contract End
Summary of Milestone Dates Contract Duration: 9 Months Compressed Duration: 4.5 Months Substantial Completion: 6 Months
Dec 19
Substantial Completion Punch List Items
29 Feb 20
Covid 19 Punch List Items
Mar 20