REA Final - 22 Dec 20 - eBook - 1682 pages

Spearhead Key Dates

Substantial Completion: 6 months vs 9 months

Spearhead Substantial Completion

Subcontract Agreement Spearhead Subcontract Agreement

30 Jan 19

Contract Milestone Start Contract Start

Apr 19

Key Milestone Dates Spearhead Start and Substantial Completion

Actual Start Date Official Spearhead start date.

14 Aug 19

BOH CO #2 Spearhead BOH CO #2

30 Aug 19

Contract Milestone End Contract End

Summary of Milestone Dates Contract Duration: 9 Months Compressed Duration: 4.5 Months Substantial Completion: 6 Months

Dec 19

Substantial Completion Punch List Items

29 Feb 20

Covid 19 Punch List Items

Mar 20

Made with FlippingBook - professional solution for displaying marketing and sales documents online