The delayed start and lack of schedule created major inefficiencies. Spearhead Planned vs Recorded Manpower Three specific issues beyond Spearhead’s control caused substantial Loss of Productivity (LOP)
55
50
333% Increase of Planned
Jan End
45
40
35
Substantial Completion
Dec End
30
25
Planned # Workers Recorded # Workers
Number of Workers
20
15
Covid Shutdown
10
5
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 Planned # Workers 9 10 10 11 11 12 12 13 13 14 14 15 15 16 17 18 19 20 20 19 18 18 17 16 15 14 13 12 11 10 8 6 5 4 3 2 2 Recorded # Workers 9 14 12 11 11 12 10 10 14 16 18 16 14 17 19 20 21 20 23 26 29 36 42 41 43 42 42 52 36 20 13 6 5 4 4 2 2 0
Week Number
Lack of Schedule Without a schedule, Spearhead executed its work with unrealistic, “whispered” end dates. The acceleration, lack of information and poor coordination created gross inefficiencies.