Spearhead Key Dates
Revised Contract Duration: 9 months Compressed Duration: 4.5 months
Spearhead Change Order Scope of Work located on Levels 1 through 4
Subcontract Agreement Spearhead Subcontract Agreement
30 Jan 19
Contract Milestone Start Date Contract Start
Apr 19
Actual Start Delayed start date
Key Milestone Dates Spearhead Added Scope of Work
14 Aug 19
BOH CO #2 Start Added Scope
30 Aug 19
1 BOH CO #2 revised Contract End Date to Dec 19. Spearhead expected to compress 9 months of work into 4.5 months duration.
1 4.5 months
Revised Milestone End Contract End
Dec 19