When: 8/27/2019, 12:00 pm
LGA - 620-027 — LGA CTB Replacement - PBB
Text We are continuing to do black iron and then stalling hangers to the black iron we also are installing the clips for the trusses. we did some layout on the third floor today. they are finishing up the fireproofing and cleaning up the rest of the fireproofing off the floor and excess materials so we could bring our lift and start framing the electric room that's skanska asked us to do Submitted By: Gary Miuccio