Spearhead, not SWJV. Assuming that Spearhead developed and submitted the schedule of values in good faith, the same should be provided as a credit.
The SWJV Ped Bridge B team and Spearhead’s estimator can meet to discuss and reconcile the cost of the credit in a professional manner, until a final dollar value is reconciled. A full accounting of cost reductions and added costs will be reconciled with the Spearhead contract as applicable to the execution of work and reduction of work upon completion of all work to avoid any further undue schedule impact.
SWJV reserves all rights and remedies under the Subcontract and at law and equity.
Sincerely,
Frank Corallo Pedestrian Bridge B Area Manager
cc.
Brian Mock Frank Corallo Scott Silverman Vince Piscopo Sean Szatkowski
Referenced Documents (not attached): 1. Spearhead Change Order – Schedule of Values 2. Spearhead-BOH COR Number LGA-620-027-21 – dated May 1, 2020 3. Skanska Walsh Letter Response to Spearhead Feb 1, 2020 letter, PBB-9925-200207-Response to Spearhead Feb 1 2020 response - Reduced Scope Bridge B.pdf 4. Skanska Walsh Letter dated April 30, 2020, PBB-10385-200429-Resp to Spearhead Credit CO Req No. 21 – BOH Work.pdf 5. Spearhead letter dated Jan 31, 2020 in response – Notice of Reduce Scope 6. Skanska Walsh Letter dated January 16, 2020 – Notice of Delays & Recovery Plan to Spearhead, PBB-9807-200116-Notice of Delays and for Recovery Plan to Spearhead.pdf
Page 2 of 2
PBB-10412-200508-Reply to Spearhead response concerning Credit COR #21 – Back of House Work