Sean – per mockup meeting with LGP, they asked to have DJV determine the minimum thickness for the joint between the GFRC and gypsum. I could not find this information previously provided. Refer to attached RFI too. Let me know if we have received this thickness elsewhere though. If not, we should submit a follow-up RFI. Thanks. Zack Trause Project Engineer

SKANSKA WALSH Design-Build Joint Venture LaGuardia Airport CTB Replacement Project Hangar 5A Runway Drive Flushing, NY 11371 Mobile: (917) 565-6140 Think twice before you press "print."

This message, including any attachments hereto, may contain privileged or confidential information and is sent solely for the attention and use of the intended addressee(s). If you are not an intended addressee, you may neither use this message nor copy nor deliver it to anyone. In such case, you should immediately destroy this message and kindly notify the sender by reply email. Thank you. The information contained in this email message is legally privileged and confidential information intended solely for the use of the intended recipient(s). If you are not the intended recipient(s), any distribution, dissemination, or reproduction of this email message is strictly prohibited. If you have received this message in error, please immediately reply to the sender and then destroy this message.

Made with FlippingBook - professional solution for displaying marketing and sales documents online