Meeting #7

Project Schedule No

Meeting Origin Title

Assignment

Due Date Priority

Status

Old/New?

5.1

1

Preliminary Schedule Review Brian Mock (SWJV) Old Description: Spearhead to update information when information becomes available regarding Plasterform/Corinthian scope. SWJV to provide information from Kone regarding installation. Previous Meeting Minutes: 3/26/2019 - Spearhead expressed concern over 12 week Vertical Transportation installation. Will need to investigate means for working in the area Kone will need. Spearhead looking at dance floor over escalator similar to HH ceiling. 3/19/2019 - SWJV to provide 6 week look ahead week of 3.15.2019. 3/12/2019 - Plasterform has indicated to Spearhead concerns meeting delivery dates starting in July. Spearhead to re-evaluate schedule 3/31/2019 Medium Open

durations by 3/31/2019 after mock-up approved. See 4/2/2019 Meeting Minutes for Previous Notes

5.3

1

Spearhead Start Date

Brian Mock (SWJV)

2/28/2019 Medium Open

Old

Description: SWJV anticipating June start date Previous Meeting Minutes: 3/26/2019 - SWJV anticipating a June start date 3/19/2019 - SWJV anticipating concrete slab to be poured week of 5/6/2019. 3/12/2019 - SWJV to re-evaluate Spearhead start date based on de-shoring and metal decking dates. Will provide update 3/19/2019. See 4/2/2019 Meeting Minutes for Previous Notes

6

Made with FlippingBook - professional solution for displaying marketing and sales documents online