REA Final - 22 Dec 20 - eBook - 1682 pages

Meeting #7

Coordination: Deliverables/Equipment/Logistics No Meeting Origin Title

Assignment

Due Date Priority

Status

Old/New?

4.1

1

GRFG Substitution Mockup Old Description: Reviewed with LGP. Spearhead to submit follow up RFI regarding control joints between GRG and GFRC. Sean Reed (Spearhead) 2/28/2019 High Open

Previous Meeting Minutes: 4/2/2019 – Mockup complete, Reviewing with LGP 4/9/2019

3/26/2019 - Spearhead will spackle and paint existing mockup. Mockup is located in Mockup room, see Zack Trause for access. 3/19/2019 - Mockup review with LGP was positive. LGP requested to see final finish on mockup. Spearhead will send finishers to perform work week of 3/25/19. Mockup has been relocated to LGP mockup room, please contact Zack Trause for access. 3/12/2019 - SWJV to get additional information/mockup requirements from LGP. No formal substitution request needed for DJV. See 4/2/2019 Meeting Minutes for Previous Notes

4.2

1

Radiator Enclosure Mockup

Doug Moore (SWJV)

3/15/2019 High

Open

Old

Description: Preliminary Shop Drawings received from Celtic. SWJV will send to Spearhead for review/comment.

Previous Meeting Minutes: 4/2/2019 – Celtic producing preliminary drawings for review and comment by SWJV 3/26/2019 - SWJV has meeting with Celtic on Wednesday at 7:30am. SWJV/Celtic/Spearhead to coordinate seam, material thickness and attachment to radiator enclosure.

3/19/2019 - SWJV will work with Celtic to provide information. 3/12/2019 - SWJV to reach out to Celtic regarding status. See 4/2/2019 Meeting Minutes for Previous Notes

4.3

1

Site Requirements - Conex Old Description: Re-Opened. Spearhead to look into using second box which could potential receive power. SWJV to send hookup cost. SWJV 3/5/2019 Medium Open

Previous Meeting Minutes: 4/2/2019 - CLOSED 3/26/2019 - Locks have been swapped. There may be a potential move to accommodate site logistics. SWJV to send logistics for employee site access based on 102 nd street work. 3/19/2019 - Rental form signed and sent to cost and logistics team. 3/12/2019 - Sean Hickey working on locations available with SWJV Logistics team. Rental information and Cost may be revised by SWJV Logistics/Cost Team. SWJV to forward revised information when available. See 4/2/2019 Meeting Minutes for Previous Notes

4.4

2

Deliveries

SWJV/Spearhead

Ongoing Low

Open

Old

Description: Previous Meeting Minutes:

4/2/2019 – Discussed site logistics for deliveries See 4/2/2019 Meeting Minutes for Previous Notes

4.5

2

Interior Fire rated Partition Old Description: Spearhead clarified detail with Hilti. The detail isn’t shown correctly. Spearhead will reference in submittal schedule. Sean Reed (Spearhead) 3/15/2019 Medium Open

Previous Meeting Minutes: 4/2/2019 – Ongoing with Hilti 3/26/2019 - Spearhead to review detail with Hilti Rep. 3/12/2019 - Spearhead will look into detail to make sure it is covered. See 4/2/2019 Meeting Minutes for Previous Notes

4.7

3

Fireproofing Coordination

Gary Miuccio (Spearhead)

3/22/2019 Low

Open

Old

4

Made with FlippingBook - professional solution for displaying marketing and sales documents online