REA Final - 22 Dec 20 - eBook - 1682 pages
Spearhead Key Dates
Contract Duration: 8 months Compressed Duration: 3.5 months
Spearhead Base Contract Scope of Work located on Pedestrian Bridge B, Level 4
Verbal Award Spearhead Informed Awarded PBB
Oct 17
Plasterform Visit Canada Trip
14 Nov 18
Subcontract Agreement Spearhead Subcontract Agreement
30 Jan 19
Spearhead Carpenter Training Day NYC Carpenters Training Facility
25 Jul 19
Milestone Start Base Contract Start
Apr 19
Key Milestone Dates Spearhead Start and End Dates
4.5 months 1
Actual Start Delayed start date
14 Aug 19
1 Milestone Start delayed 4.5 months. 2 Without a change to its end date, Spearhead expected to compress 8 months of work into 3.5 months.
3.5 months 2
Milestone End Base Contract End
Nov 19