Submittal #PedBB-0468 . 1 09290 - Gypsum Board Assemblies

HOK

Project: LGA620.1 - Concourse B Bridge LaGuardia Airport Hangar 5A Runway Drive Flushing, New York 11371

SWJV LaGuardia Airport Hangar 5A, Runway Drive Flushing, New York 11371

RECEIVED 01/28/2020

PedBB - Feature Wall Ceiling Support

SPEC SECTION:

CREATED BY:

09290 - Gypsum Board Assemblies 

STATUS:

DATE CREATED:

Open

01/27/2020 

ISSUE DATE: RESPONSIBLE CONTRACTOR: RECEIVED DATE: REQUESTED RESPONSE DATE: FINAL DUE DATE: TAA NUMBER(S) DJV SUBMITTAL # SWJV DISAGREES WITH CA SUBMITTAL CLASSIFICATION: RELATED TO LGP/PA CHANGE ORDER: TYPE:

REVISION:

01/27/2020  

1

RECEIVED FROM:

Sean Reed

Spearhead Construction LLC

SUBMIT BY:

01/21/2020

01/27/2020  

SUBMITTED FOR:  Approval

LOCATION:

02/07/2020

PBB - Area BF 

Shop Drawing

3147.07

----

SWJV REASON FOR DISPUTING CA CLASSIFICATION: LGP/PA CHANGE ORDER NO.:

No  

No  

APPROVERS:

Peter Costanzo (HOK)

BALL IN COURT: Peter Costanzo (HOK) DISTRIBUTION:

LGA Email (HOK) , Mildred Campos (HOK) , Zachary Trause (Skanska Walsh JV) , Enrico Tomassoli (HOK) , Shayon Shahi (Skanska Walsh JV) , Tej Savalia (Skanska Walsh JV) , Me ko  Sato  (HOK) , Kevin Peters (HOK) , Douglas Moore (Skanska Walsh JV) , Brian P. Mock (Skanska Walsh JV) , Francesca Meola (HOK) , Kate McPhillips (WSP-PBHOK JV) , Brady Lawler (Skanska Walsh JV) , Mackenzie Kirby (Skanska Walsh JV) , Justin Jennings (HOK) , Sean Hickey (Skanska Walsh JV) , Mark Hendel (HOK) , Radhika  Deshpande  (HOK) , Frank Corallo (Skanska Walsh JV) , James Christerson (HOK) , Bill Carson (Skanska Walsh JV) , Murat Bilgen (Skanska Walsh JV)

DESCRIPTION: ATTACHMENTS: PB-922-09290-0468-R1 Feature Wall Ceiling Support 20200127.pdf

SUBMITTAL WORKFLOW # NAME

SUBMITTER/ APPROVER SENT DATE DUE DATE RETURNED DATE RESPONSE ATTACHMENT S

COMMENTS

LaGuardia Airport Central Terminal Building Replacement Project

GRAVITY CONNECTION TO ROOF DECK NOT ACCEPTABLE (SEE STRUCTURAL GENERAL NOTE 1.5.F ON S05-AJ-02-00-00). REVISE TO SUPPORT WALL FROM STRUCTURAL STEEL. REFER TO PEDBA FEATURE WALL SUBMITTAL FOR POTENTIAL FRAMING SCHEME. FRAMING SUBMITTAL SHOULD ACCOUNT FOR VERTICAL GWB ON METAL STUD FIRE BLOCKING EVERY 10' MAX. SEE A57-25-00-00-00 (RIDER B).

1

Peter Costanzo

g

Parsons Brinckerhoff / HOK Design Joint Venture

May proceedwth theWork covered by ths Submitalpovided it compieswth theContract Documents Comments and correctons do not authorze changes to theContactDocuments Donot proceedwith theWork covered by this Submital Limt corectons in resubmissions to tems noed in thisSubmttal

A B C D

Approved Approved as Noted Revise as Noted and Resubmit Rejected Reviewed for Information as Noted Reviewed for Information

E F

ThsSubmital s for informatononly Resubmt only if noted in ths submttal

C

Revise as Noted and Resubmit

Review of thisSubmittal is for the limited purposeof checking for conformancewith information given and thedesign concept expressed in theContractDocuments.The review s not fordetermining theaccuracy or competeness of otherdetals suchas dimensionsand quanities, or for subsantating instructions for instalationor performance ofequipmentor sysems,which remains theContractors responsibilty. Review shall not constituteapprovalof safety precautons,or of constructionmeans, methods,and techniques, sequences or procedures. Approval of a specific item shall not indicate approvalofan assembly ofwhich the item is a component.This review shallnot serve asawarranty or thebenefit of the contracor.

RevewedBy:

Justin Jennings - HOK 01/29/2020

SubmttalFle:

PB-0922-09290-0468-R1 Feature Wall Ceiling Support.pdf

SWJV

Printed On: 01/28/2020  02 :29 PM