Brooklyn Children's Museum Additional Labor Costs Due to Covid-19

Brooklyn Children’s Museum Auditorium Fit-Out Project PV262-AUD: Additional Labor Costs Due to Covid-19

March 2022

March 3, 2022

Sean Bronson Executive Project Manager XBR Inc. 35-12 19 th Avenue, Suite 2E Astoria, NY 12210 RE: RESUBMISSION - SPEARHEAD COVID-19 INCURRED COSTS CLAIM / COR 11 R2 Project: BCM – PV262 – AUD Brooklyn Children’s Museum Auditorium Mr. Bronson: Spearhead Construction, LLC (“Spearhead”) provides the following, additional information to clarify the added expense to comply with New York State Department of Health, New York City Department of Design and Construction, and New York City Department of Buildings (“Agencies”) mandates and site-specific requirements, located in the references below, for performing construction during the COVID-19 pandemic at the Brooklyn Children’s Museum Auditorium. References: 1. NY Forward Business Re-Opening Safety Plan Template 2. New York State Department of Health Interim Guidance for Construction Activities During the Covid-19 Public Health Emergency, 2020. 3. NYC Department of Design and Construction COVID-19 – Construction Sites Safety Protocol Reconstitution Phase, June 2020. 4. New York State Department of Health Guidance on the Contacts of a Close or Proximate Contact of a Confirmed or Suspected Case of COVID-19. 5. NYC Department of Design and Construction COVID-19 Recommended Practices for Construction Jobsites. 6. NYC Buildings Phase 1: NYC Construction Restart. 7. Pandemics and Productivity: Quantifying the Impact – New Horizons Foundation, July 2020. 8. Empirical Productivity Impacts of the Novel Coronavirus 1 st Edition – J S Held University, 2020. 9. Impact of Covid-19 on Field and Office Workforce in Construction Industry – Project Leadership and Society, December 2021. Clarification: Different Site Conditions – New, Added Tasks Compliance with the Agencies’ and site specific COVID-19 procedures caused additional work steps, which were not anticipated at time of bid nor included as part of the Contract documents. These different site conditions caused added work steps resulting in unplanned, additional labor hours beyond the contracted scope of work. As a matter of public safety, the Agencies, Owner, and General Contractor (GC) required Spearhead to perform additional tasks, which resulted in

Spearhead Construction, LLC PO BOX 575 Fort Montgomery, NY 10922

incurred costs of additional labor hours. These new, added tasks for each worker, are summarized in the following Table 1.

Spearhead Extra Work for Covid-19 Protocols Table 1

Minutes / workday

Hours / workday

Extra Work Task

Daily health screening and temperature check

6

0.10 0.17 0.03 0.05 0.10

End of day tool cleaning

10

Social Distancing

2

Daily and weekly administrative record keeping

3 6

Additional hydration, personal hygiene, extra handwashing

Mask mandate - labored breathing, physical fatigue, obscured vision (fogged eyewear), additional hydration, and mental fatigue reduced effectiveness by a minimum of 10% (6 minutes per work hour, or 48 mins per 8 hour workday)

48

0.80

75

1.25

Extra time devoted to Covid-19 Compliance Protocols (per 8 hour workday)

Different Site Conditions - New, Added Tasks Prior to Commencement of Work Due to differing site conditions caused by the unprecedented COVID-19 event, additional tasks were required at the start of each workday. An average of six Spearhead workers stood in line and waited to have their temperatures measured and recorded. Workers had to verbally confirm no COVID-19 symptoms to the Foreman. Additionally, to adhere to the Agencies’ guidelines, workers were also required to complete an electronic COVID-19 self-reporting form on Monday mornings. Prior to work assignments: 1. daily health screening questions and temperature readings, (+ 6 mins / workday) 2. weekly confirmation that workers had not returned from restricted COVID areas, 3. daily protocol information entered and submitted to office. (+3 mins/workday) • Once all workers were deemed “fit for duty,” the Foreman assigned crews and tasks, while taking into consideration social distancing throughout each area of the jobsite. Screening, administrative tasks, crew reassignment, and daily temperature readings amounted to nine additional minutes per worker, per workday. For reference, morning assignments of Spearhead average crew size of six workers in a pre-pandemic environment typically accounted for 10—15 minutes. During Spearhead’s work at Brooklyn Children’s Museum, morning assignments increased from 10—15 minutes to 19—24 minutes because of these added tasks.

Spearhead Construction, LLC PO BOX 575 Fort Montgomery, NY 10922

• Additionally, Spearhead’s Foreman had to verify the information for accuracy and ensure workers completed the Spearhead Covid-19 Weekly Screening information then submit electronic copies to office staff for collection, review, tracking, and filing as part of the change in site conditions on a weekly basis. Each of these new, added tasks required additional time that employees would have otherwise spent performing job tasks during pre-pandemic conditions. Clarification: Quantifying Additional Labor Hours Resulting from New, Added Tasks Workers were also impacted throughout their workday because of different site conditions stemming from compliance with the Agencies’ guidelines. Spearhead incurred additional labor expenses beyond its contracted scope of work and quantified the added time of six minutes per hour, or 48 minutes per 8 hour workday, by worker. 1 Throughout workday: 1. social distancing - change in means and methods, (+2 mins / workday) 2. daily fatigue of wearing of additional PPE, (+6 mins / work hour or + 48 mins / 8 hour workday) 3. additional hand washing, sanitization, and hygiene measures, (+ 6 mins / workday) 4. daily disinfection of tools and materials, (+10 mins / workday). Different Site Conditions - New, Added Tasks Throughout Workday The additional 48 minutes per worker, per 8 hour workday, is in line with the Nationwide study, Pandemics and Productivity: Quantifying the Impact report, which is included in this eBook for reference. Please note that the study focused on “fit-for-duty” mandates that were identical to the requirements of Spearhead workers, regardless of specialty trade. The comparison of the findings in the study to Spearhead’s actual hours expended is valid and offered as additional justification of its claim. The following factors contributed to the additional six minutes per hour: social distancing, increased Personal Protection Equipment (PPE), fatigue and dehydration, material handling, increased water consumption, extra handwashing, and additional rest times. Social Distancing caused Spearhead to change its means and methods. • Adherence to COVID-19 social distancing procedures required Spearhead to implement newmeans and methods for crew assignments. Prior to COVID-19, Spearhead could have multiple crews working simultaneously in the same area. However, in attempting to limit potential COVID-19 exposures, crews had to work independently, in different locations from one another and from other trades. Whenever possible, crews were maintained from day-to-day without mixing personnel.

1 In February 2021, Spearhead moved from an 8 hour workday to a 7 hour workday due to limited, available work areas. Spearhead calculated added time based on 6 minutes per hour worked.

Spearhead Construction, LLC PO BOX 575 Fort Montgomery, NY 10922

• In pre-pandemic conditions, Spearhead typically completed taping and finishing with one crew working simultaneously in a space as a team and in an assembly line fashion. Crew members focused on specific tasks and worked efficiently, in tandem with one another. However, due to social distancing requirements, Spearhead crews had to switch between various tasks to limit the number of personnel in each area at the same time, which added time to complete the work. Each of these new, added tasks required additional time that employees would have otherwise spent performing job tasks during pre-pandemic conditions. New PPE requirements caused an increase in physical exertion to complete tasks. The burden of wearing a mask in a construction environment is different than wearing a mask in an office setting. Neither scenario is ideal, but construction workers expend far more energy throughout the day. • Fatigue: Spearhead workers handled materials by accepting and unloading deliveries, carrying materials to specific work locations and installing materials. At the Brooklyn Children’s Museum project, workers had to unload materials from delivery trucks parked more than 400 feet from building, move materials across two floor levels and hand individual pieces up to a scaffold platform. Handling 200- to 300-pound Glass Fiber Reinforced Gypsum (GFRG) panels, 64-pound buckets of finishing compound and other construction materials required additional exertion and time to complete work tasks due to breathing through a facemask, which led to labored breathing, an increased need for hydration, and resulted in greater fatigue. • Obscured Vision/Fogged Eyewear: After moving materials to their final place of rest, workers had to hoist these heavy GFRG panels up to 8 feet above the platform to install and finish the GFRG panels at the ceiling. Wearing a facemask also caused an increase in physical exertion which led to labored breathing. The warm, moist air moving through the facemask also led to condensation of protective eyewear. Workers had to stop, periodically, and wipe the glasses clear, which added more time and frustration to complete their tasks. • Dehydration: To illustrate the effects of COVID-19 safety procedures on the fatigue and dehydration levels of workers, on average in pre-pandemic conditions, workers consumed two bottles of water per day provided by Spearhead. However, during COVID- 19, workers at the Brooklyn Children’s Museum project consumed an average of four bottles of water per day to replenish electrolytes caused by physical exertion while breathing through a mask all day.

• Personal Hygiene: Mask wearing requirements necessitated additional water breaks as a direct result of fatigue, dehydration, and a need to urinate more frequently. Workers

Spearhead Construction, LLC PO BOX 575 Fort Montgomery, NY 10922

required additional time to clean their hands with sanitizer prior to retrieving water from a central location, consuming the water, and defogging safety glasses. After using the latrine, workers had to clean hands with sanitizer, again. Each of these new, added tasks required additional time that employees would have otherwise spent performing job tasks during pre-pandemic conditions. Mental Fatigue Added Time to daily tasks The COVID pandemic was, and continues to be, an unprecedented social, health, and economic disaster not only affecting the world at large, families, and individuals, but also construction workers, specifically. No one could have predicted the impact the pandemic would have on worker shortages, supply chain disruptions, or the stability of workforce psyche plagued with fears of contracting the virus, potentially exposing family members, or the financial implications of work stoppages or shutdowns. The Elsevier study, Impact of Covid-19 on Field and Office Workforce in Construction Industry, indicates that across the construction industry, workers experienced increased anxiety and trauma as a result of fear of exposure to the life-threatening virus, particularly when multiple subcontractors were working on site near one another. Throughout the course of this project, test sites and test kits were in high demand with limited supply. Medical experts grappled not only with finding the most effective and reliable treatment but also for space to treat the sickest patients. Deaths skyrocketed every month. • This project site was conducive to spreading the virus by nature of working indoors, with no windows, or outside ventilation, amongst multiple tradesmen. Spearhead had an average of six workers on site each day. Other trades had a similar number of workers, all in close proximity. The jobsite lacked a handwashing station and workers had to rely on personal hand sanitizers. Without a vaccine, the only tools workers had to combat the spread of the virus was relentless vigilance in wearing a mask, personal hygiene with hand sanitizers, and daily cleaning of tools, materials, and equipment. • Meanwhile, Spearhead leadership had to closely monitor worker health, review daily questionnaires, and take steps to remove workers who had potentially been exposed to the virus or who presented with symptoms of the virus. • Workforce mental fatigue caused by the virus and additional precautions resulted in increased callouts. Locating additional labor in a timely manner proved difficult for Union leaders. Workers who remained on site experienced increased stress and anxiety for fear of exposure or infection by those who did not always wear a mask, required testing, or tested positive. Mental fatigue led to increased exhaustion and required additional time that workers would have otherwise spent performing job tasks during pre-pandemic conditions.

Spearhead Construction, LLC PO BOX 575 Fort Montgomery, NY 10922

End of Day Clean up Added Time to Daily Tasks Finally, workers were impacted at the end of their workday, as well. Prior to completing their workday, workers were required to individually sanitize tools and materials that they were in contact with throughout the day, above and beyond just returning tools to lockboxes as in pre- pandemic conditions. Due to the fluid nature of our national understanding of the pandemic, workers left the site more exhausted than normal and unsure what changes might be required of them in the following days. Conclusion Added tasks, time to complete the new tasks, and incurred labor costs of properly and safely maintaining caution in a virus-ridden environment contributed to additional project hours and out-of-pocket costs to Spearhead. The extra labor hours required to complete the work and tasks were a direct result of the COVID-19 pandemic and were in addition to contract requirements, known existing conditions at time of bid, and what could have been reasonably expected of any subcontractor at the time of the estimate and signing of the Brooklyn Children’s Museum contract. Lastly, Spearhead includes in this package an updated hours breakdown through the end of the project. As such, the revised COR 11 R2 totals $100,904 of additional costs to comply with Agencies’ Covid-19 protocols.

Due to file size constraints, Spearhead created an eBook containing documentation for its claim:

Spearhead eBook: BCM PV262-AUD – Additional Labor Costs Due to Covid-19 Password: Si7&Cx@90BX#Ee)

Spearhead handled and installed over 25,000 pounds of construction materials and equipment multiple times, throughout the Auditorium, while wearing a face mask, steaming up protective eyewear, fighting fatigue and stress. Denying this request for reimbursement is unrealistic as Spearhead and its workforce literally shouldered the weight of this New York City project to finance the full expense of these added tasks. The lack of reimbursement for these out-of-scope requirements, different site conditions, and non-contracted work tasks, carried for over a year, continues to financially harm Spearhead Construction.

Thank you for your reconsideration of this valid claim.

Respectfully,

Andee Hidalgo Owner and President

Spearhead Construction, LLC PO BOX 575 Fort Montgomery, NY 10922

Attachments:

COR 11 R2 COVID-19 Incurred Costs for Labor (Final) Spearhead eBook: BCM Fit-Out Project PV262-AUD – Additional Labor Costs Due to Covid-19

Cc:

Brandon Millner, Lea Case, Ashton Summors, Catherine Park, Rose Marquez, Woon Lam, Ira Grunther, Rose Ott, John Stanforth, Peter Lambrakis, Nalini Sadloo

Spearhead Construction, LLC PO BOX 575 Fort Montgomery, NY 10922

Change Order Request

BCM - PV262-AUD — Brooklyn Children's Museum Auditorium

COR Subject: COVID-19 Incurred Costs for Labor (Final)

BCM - PV262- AUD-11

To

Sean Bronson XBR Inc 35-12 19th Avenue Suite 2E Astoria, NY 11105 718-606-0072 718-889-2229 (FAX) John Stanforth Spearhead Construction 805.816.7492 john@spearheadcx.com

COR Number:

COR Revision Number: 2

COR Date: 2/28/2022 Work Type: Work Under Protest Days Valid: 5

Return To

Scope Of Work / Time Extension Request Incurred labor costs due to complying with mandated DOH COVID-19 protocols. Please see attached supporting documentation and letter of explanation.

Details

Cost / Rate

Qty / Hrs

Description

Workers

Ext

145.36 Hrs

Foreman

$132.14

1.00

$19207.87

Wage Rate Period: 1 July 2020 to 30 Jun 2021

4.36 Hrs

Foreman

$132.58

1.00

$578.05

Wage Rate Period: 1 July 2021 to 30 Jun 2022

454.80 Hrs

Journeyman

$123.98

1.00

$56386.10

Wage Rate Period: 1 July 2020 to 30 Jun 2021

12.62 Hrs

Journeyman

$125.09

1.00

$1578.64

Wage Rate Period: 1 July 2021 to 30 Jun 2022

34.10 Hrs

Finisher

$93.63

1.00

$3192.78

Cost / Rate

Qty / Hrs

Description

Workers

Ext

Wage Rate Period: 1 July 2020 to 30 Jun 2021

10.12 Hrs

Finisher

$94.78

1.00

$959.17

Wage Rate Period: 1 July 2021 to 30 Jun 2022

Breakout

Labor : $81,902.61 Overhead Percent @ 23.2%: $19,001.41 _____________ Total: $100,904.02

Reservation of Rights This COR does not include any amount for impacts such as interference, disruptions, rescheduling, changes in the sequence of work, delays and/or associated acceleration. Spearhead Construction, LLC expressly reserves the right to submit our request for any of these items.

Signed By:

Dated: 2/28/2022

__________________________

S pearhead Construction Labor Hours for Covid Procedures

BCM- PV262-AUD - Brooklyn Children'sMuseum Auditorium

Effective: 9 Jun 20

A

B

C

D

E

F

G

H

Extra Time Devoted to Covid-19 Protocols (in Hours)

Date Worked Cost Code Description

Labor Class

Labor Type Hours Worked

Billable Rate Incurred Cost (Column F x G)

7/6/20 SUPERVISION - FOREMAN

Foreman

Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter

8 4 4 4 4 8 8 2 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 1 7 1 7 1 7 1 7 8 8 8 8 8 8 8 8 8 8 8

1.25 0.63 0.63 0.63 0.63 1.25 1.25 0.31 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 0.16 1.09 0.16 1.09 0.16 1.09 0.16 1.09 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25

$132.14 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $132.14 $123.98 $123.98 $132.14 $123.98 $123.98 $132.14 $123.98 $123.98 $132.14 $123.98 $123.98 $132.14 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $132.14 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98

$165.18 $78.11 $78.11 $78.11 $78.11 $165.18 $154.98 $38.43 $154.98 $165.18 $154.98 $154.98 $165.18 $154.98 $154.98 $165.18 $154.98 $154.98 $165.18 $154.98 $154.98 $165.18 $154.98 $154.98 $165.18 $154.98 $154.98 $165.18 $154.98 $154.98 $154.98 $21.14 $144.03 $19.84 $135.14 $19.84 $135.14 $19.84 $135.14 $165.18 $154.98 $154.98 $154.98 $165.18 $154.98 $154.98 $154.98 $165.18 $154.98 $154.98

7/6/20 LOAD & DIST - METAL 20 & 25 GA

Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Foreman

7/6/20 FRAME -WALLS

7/6/20 LOAD & DIST - METAL 20 & 25 GA

7/6/20 FRAME -WALLS

7/7/20 SUPERVISION - FOREMAN

7/7/20 FRAME -WALLS 7/7/20 FRAME -WALLS 7/7/20 FRAME -WALLS

7/8/20 SUPERVISION - FOREMAN

Foreman

7/8/20 FRAME -WALLS 7/8/20 FRAME -WALLS

Journeyman Journeyman

7/9/20 SUPERVISION - FOREMAN

Foreman

7/9/20 FRAME - SOFFITS 7/9/20 FRAME - SOFFITS

Journeyman Journeyman

7/10/20 SUPERVISION - FOREMAN

Foreman

7/10/20 FRAME - SOFFITS 7/10/20 FRAME - SOFFITS

Journeyman Journeyman

7/13/20 SUPERVISION - FOREMAN

Foreman

7/13/20 FRAME - SOFFITS 7/13/20 FRAME - SOFFITS

Journeyman Journeyman

7/14/20 SUPERVISION - FOREMAN

Foreman

7/14/20 FRAME - SOFFITS 7/14/20 FRAME - SOFFITS

Journeyman Journeyman

7/15/20 SUPERVISION - FOREMAN

Foreman

7/15/20 FRAME - CEILING 7/15/20 FRAME - CEILING

Journeyman Journeyman

7/16/20 SUPERVISION - FOREMAN 7/16/20 INSTALL - GWB OVER 9' 7/16/20 INSTALL - GWB OVER 9' 7/16/20 INSTALL -WOOD BLOCKING 7/17/20 SUPERVISION - FOREMAN 7/17/20 Extra Directed Work 7/17/20 FRAME - SOFFITS 7/17/20 Extra Directed Work 7/17/20 TAPING - CEILINGS 7/17/20 Extra Directed Work 7/17/20 FRAME - SOFFITS 7/17/20 Extra Directed Work 7/20/20 Extra Directed Work 7/20/20 Extra Directed Work 7/20/20 Extra Directed Work 7/20/20 Extra Directed Work 7/21/20 Extra Directed Work 7/21/20 Extra Directed Work 7/21/20 Extra Directed Work 7/21/20 Extra Directed Work 7/22/20 SUPERVISION - FOREMAN

Foreman

Journeyman Journeyman Journeyman

Foreman Foreman

Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Foreman Foreman

Foreman

7/22/20 FRAME - SOFFITS 7/22/20 FRAME - SOFFITS

Journeyman Journeyman

S pearhead Construction Labor Hours for Covid Procedures

BCM- PV262-AUD - Brooklyn Children'sMuseum Auditorium

Effective: 9 Jun 20

A

B

C

D

E

F

G

H

Extra Time Devoted to Covid-19 Protocols (in Hours)

Date Worked Cost Code Description

Labor Class

Labor Type Hours Worked

Billable Rate Incurred Cost (Column F x G)

7/22/20 FRAME - SOFFITS

Journeyman

Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter

8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 3 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8

1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 0.47 0.63 0.63 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25

$123.98 $132.14 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $132.14 $132.14 $123.98 $132.14 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $132.14 $132.14 $132.14 $132.14 $132.14 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $132.14

$154.98 $165.18 $154.98 $154.98 $154.98 $165.18 $154.98 $154.98 $154.98 $165.18 $154.98 $154.98 $154.98 $165.18 $154.98 $154.98 $154.98 $62.11 $83.25 $78.11 $165.18 $154.98 $165.18 $154.98 $154.98 $154.98 $154.98 $165.18 $165.18 $165.18 $165.18 $165.18 $154.98 $154.98 $165.18 $154.98 $154.98 $154.98 $154.98 $165.18 $154.98 $154.98 $154.98 $154.98 $165.18 $154.98 $154.98 $154.98 $154.98 $165.18

7/23/20 SUPERVISION - FOREMAN

Foreman

7/23/20 FRAME - SOFFITS 7/23/20 FRAME - SOFFITS 7/23/20 FRAME - SOFFITS

Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Foreman Foreman Foreman

7/24/20 SUPERVISION - FOREMAN 7/24/20 INSTALL - BATT INSULATION 7/24/20 INSTALL - BATT INSULATION 7/24/20 INSTALL - BATT INSULATION 7/27/20 Extra Directed Work 7/27/20 Extra Directed Work 7/27/20 Extra Directed Work 7/27/20 Extra Directed Work 7/28/20 SUPERVISION - FOREMAN 7/28/20 INSTALL - GWB SOFFIT 7/28/20 INSTALL - GWB SOFFIT 7/28/20 INSTALL - GWB SOFFIT 10/16/20 SUPERVISION - FOREMAN 10/28/20 SUPERVISION - FOREMAN 10/28/20 LOAD & DIST - MISC ITEMS 11/17/20 SUPERVISION - FOREMAN

Foreman Foreman

4.5 4.5

Journeyman

Foreman

11/17/20 INSTALL - GWB (STAND UP BOARDS UP TO 9')

Journeyman

11/18/20 INSTALL - FRG 11/18/20 TAPING -WALLS 11/18/20 INSTALL - FRG 11/25/20 TAPING -WALLS

Foreman

Journeyman Journeyman Journeyman Journeyman

12/1/20 TAPING AND FINISHING

1/7/21 MOBE

Foreman Foreman Foreman Foreman Foreman

1/19/21 SUPERVISION - FOREMAN 1/20/21 SUPERVISION - FOREMAN 1/21/21 SUPERVISION - FOREMAN 1/22/21 SUPERVISION - FOREMAN

1/22/21 LOAD & DIST - METAL 20 & 25 GA 1/22/21 LOAD & DIST - METAL 20 & 25 GA

Journeyman Journeyman

1/25/21 SUPERVISION - FOREMAN

Foreman

1/25/21 FRAME -WALLS 1/25/21 FRAME -WALLS 1/25/21 FRAME -WALLS 1/25/21 FRAME -WALLS

Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Foreman Foreman

1/26/21 SUPERVISION - FOREMAN

1/26/21 FRAME - SOFFITS 1/26/21 FRAME - SOFFITS

1/26/21 LOAD & ACCEPT RENTAL EQUIPMENT 1/26/21 LOAD & ACCEPT RENTAL EQUIPMENT 1/27/21 LAYOUT -WALLS & COLUMNS

1/27/21 FRAME - SOFFITS 1/27/21 FRAME - SOFFITS

1/27/21 LOAD & DIST - BLACK IRON 1/27/21 LOAD & DIST - BLACK IRON 1/28/21 SUPERVISION - FOREMAN

Foreman

S pearhead Construction Labor Hours for Covid Procedures

BCM- PV262-AUD - Brooklyn Children'sMuseum Auditorium

Effective: 9 Jun 20

A

B

C

D

E

F

G

H

Extra Time Devoted to Covid-19 Protocols (in Hours)

Date Worked Cost Code Description

Labor Class

Labor Type Hours Worked

Billable Rate Incurred Cost (Column F x G)

1/28/21 INSTALL - GWB (STAND UP BOARDS UP TO 9') 1/28/21 INSTALL - GWB (STAND UP BOARDS UP TO 9')

Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Foreman Foreman Foreman Foreman Foreman Foreman

Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter

8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 2 6 2 6 4 4 4 4 8 8 8

1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 0.31 0.94 0.31 0.94 0.63 0.63 0.63 0.63 1.25 1.25 1.25

$123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98

$154.98 $154.98 $154.98 $154.98 $165.18 $154.98 $154.98 $154.98 $154.98 $165.18 $154.98 $154.98 $154.98 $154.98 $154.98 $165.18 $154.98 $154.98 $154.98 $154.98 $154.98 $154.98 $165.18 $154.98 $154.98 $154.98 $154.98 $154.98 $154.98 $165.18 $154.98 $154.98 $154.98 $154.98 $154.98 $154.98 $165.18 $154.98 $154.98 $38.43 $116.54 $38.43 $116.54 $78.11 $78.11 $78.11 $78.11 $165.18 $154.98 $154.98

1/28/21 LOAD & DIST - BLACK IRON 1/28/21 LOAD & DIST - BLACK IRON 1/29/21 SUPERVISION - FOREMAN

1/29/21 INSTALL - GWB (STAND UP BOARDS UP TO 9') 1/29/21 INSTALL - GWB (STAND UP BOARDS UP TO 9')

1/29/21 LOAD & DIST - BLACK IRON 1/29/21 LOAD & DIST - BLACK IRON 2/3/21 LOAD & DIST - FRG 2/3/21 LOAD & DIST - FRG 2/3/21 LOAD & DIST - FRG 2/3/21 LOAD & DIST - FRG 2/3/21 LOAD & DIST - FRG 2/3/21 LOAD & DIST - FRG 2/4/21 INSTALL - FRG 2/4/21 INSTALL - FRG 2/4/21 FRAME -WALLS 2/4/21 FRAME -WALLS 2/5/21 INSTALL - FRG 2/5/21 INSTALL - FRG 2/5/21 FRAME -WALLS 2/5/21 FRAME -WALLS 2/5/21 FRAME - CEILING 2/5/21 FRAME - CEILING 2/8/21 Extra Directed Work 2/8/21 Extra Directed Work 2/8/21 Extra Directed Work 2/8/21 INSTALL - BLACK IRON 2/8/21 INSTALL - BLACK IRON 2/9/21 SUPERVISION - FOREMAN 2/4/21 SUPERVISION - FOREMAN 2/4/21 INSTALL - BLACK IRON 2/4/21 INSTALL - BLACK IRON 2/5/21 SUPERVISION - FOREMAN 2/8/21 INSTALL - FRG 2/8/21 INSTALL - FRG

2/9/21 INSTALL - FRG 2/9/21 INSTALL - FRG

2/9/21 Extra Directed Work 2/9/21 LOAD & DIST - FRG 2/9/21 Extra Directed Work 2/9/21 LOAD & DIST - FRG

2/9/21 INSTALL - FRG

2/9/21 INSTALL - BLACK IRON

2/9/21 INSTALL - FRG

2/9/21 INSTALL - BLACK IRON 2/10/21 SUPERVISION - FOREMAN

Foreman

2/10/21 INSTALL - FRG 2/10/21 INSTALL - FRG

Journeyman Journeyman

S pearhead Construction Labor Hours for Covid Procedures

BCM- PV262-AUD - Brooklyn Children'sMuseum Auditorium

Effective: 9 Jun 20

A

B

C

D

E

F

G

H

Extra Time Devoted to Covid-19 Protocols (in Hours)

Date Worked Cost Code Description

Labor Class

Labor Type Hours Worked

Billable Rate Incurred Cost (Column F x G)

2/10/21 INSTALL - GWB OVER 9' 2/10/21 INSTALL - GWB OVER 9' 2/10/21 INSTALL - BLACK IRON 2/10/21 INSTALL - BLACK IRON 2/11/21 SUPERVISION - FOREMAN

Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Foreman Foreman Foreman Foreman Foreman Foreman Foreman

Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter

8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7

1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.25 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09

$123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98

$154.98 $154.98 $154.98 $154.98 $165.18 $154.98 $154.98 $154.98 $154.98 $154.98 $165.18 $154.98 $154.98 $154.98 $154.98 $154.98 $154.98 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14

2/11/21 INSTALL - FRG 2/11/21 INSTALL - FRG 2/11/21 INSTALL - FRG

2/11/21 INSTALL - HMBUCKS 2/11/21 INSTALL - HMBUCKS 2/12/21 SUPERVISION - FOREMAN

2/12/21 INSTALL - FRG 2/12/21 INSTALL - FRG

2/12/21 INSTALL - GWB (STAND UP BOARDS UP TO 9') 2/12/21 INSTALL - GWB (STAND UP BOARDS UP TO 9')

2/12/21 INSTALL - BLACK IRON 2/12/21 INSTALL - BLACK IRON 2/16/21 SUPERVISION - FOREMAN

2/16/21 INSTALL - FRG 2/16/21 INSTALL - FRG 2/16/21 INSTALL - FRG 2/16/21 INSTALL - FRG

2/16/21 INSTALL - FIRE CAULKING 2/16/21 INSTALL - FIRE CAULKING 2/17/21 SUPERVISION - FOREMAN

2/17/21 INSTALL - FRG 2/17/21 INSTALL - FRG 2/17/21 INSTALL - FRG 2/17/21 INSTALL - FRG

2/17/21 INSTALL - GWB (STAND UP BOARDS UP TO 9') 2/17/21 INSTALL - GWB (STAND UP BOARDS UP TO 9')

2/18/21 SUPERVISION - FOREMAN

7.5

2/18/21 INSTALL - FRG 2/18/21 INSTALL - FRG 2/18/21 INSTALL - FRG 2/18/21 INSTALL - FRG

2/18/21 INSTALL -WOOD BLOCKING 2/18/21 INSTALL -WOOD BLOCKING 2/19/21 SUPERVISION - FOREMAN

2/19/21 INSTALL - FRG 2/19/21 INSTALL - FRG 2/19/21 INSTALL - FRG 2/19/21 INSTALL - FRG

2/19/21 INSTALL -WOOD BLOCKING 2/19/21 INSTALL -WOOD BLOCKING 2/22/21 SUPERVISION - FOREMAN

2/22/21 INSTALL - FRG 2/22/21 INSTALL - FRG 2/22/21 INSTALL - FRG 2/22/21 INSTALL - FRG

S pearhead Construction Labor Hours for Covid Procedures

BCM- PV262-AUD - Brooklyn Children'sMuseum Auditorium

Effective: 9 Jun 20

A

B

C

D

E

F

G

H

Extra Time Devoted to Covid-19 Protocols (in Hours)

Date Worked Cost Code Description

Labor Class

Labor Type Hours Worked

Billable Rate Incurred Cost (Column F x G)

2/22/21 INSTALL - BLACK IRON 2/22/21 INSTALL - BLACK IRON 2/23/21 SUPERVISION - FOREMAN 2/23/21 INSTALL - FRG 2/23/21 INSTALL - FRG 2/23/21 INSTALL - FRG 2/23/21 INSTALL - FRG 2/23/21 INSTALL - FRG 2/23/21 INSTALL - FRG 2/24/21 INSTALL - FRG 2/24/21 INSTALL - FRG 2/24/21 INSTALL - FRG 2/24/21 INSTALL - FRG 2/24/21 INSTALL - FRG 2/24/21 INSTALL - FRG 2/25/21 INSTALL - FRG 2/25/21 INSTALL - FRG 2/25/21 LOAD & DIST - FRG 2/25/21 LOAD & DIST - FRG 2/25/21 LOAD & DIST - FRG 2/25/21 LOAD & DIST - FRG 2/26/21 INSTALL - FRG 2/26/21 INSTALL - FRG 2/26/21 INSTALL - FRG 2/26/21 INSTALL - FRG 2/26/21 FRAME -WALLS 2/26/21 FRAME -WALLS 3/1/21 INSTALL - FRG 3/1/21 INSTALL - FRG 3/1/21 INSTALL - FRG 3/1/21 INSTALL - FRG 3/1/21 FRAME -WALLS 3/1/21 FRAME -WALLS 2/24/21 SUPERVISION - FOREMAN 2/25/21 SUPERVISION - FOREMAN 2/26/21 SUPERVISION - FOREMAN 3/1/21 SUPERVISION - FOREMAN 3/2/21 SUPERVISION - FOREMAN

Journeyman Journeyman

Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter

7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7

1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09

$123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98

$135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14

Foreman

Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Foreman Foreman Foreman Foreman Foreman Foreman

3/2/21 INSTALL - FRG 3/2/21 INSTALL - FRG

3/2/21 INSTALL - GWB (STAND UP BOARDS UP TO 9') 3/2/21 INSTALL - GWB (STAND UP BOARDS UP TO 9')

3/2/21 INSTALL -WOOD BLOCKING 3/2/21 INSTALL -WOOD BLOCKING 3/3/21 SUPERVISION - FOREMAN

3/3/21 INSTALL - FRG 3/3/21 INSTALL - FRG

3/3/21 INSTALL - GWB (STAND UP BOARDS UP TO 9') 3/3/21 INSTALL - GWB (STAND UP BOARDS UP TO 9')

3/3/21 INSTALL - BLACK IRON

S pearhead Construction Labor Hours for Covid Procedures

BCM- PV262-AUD - Brooklyn Children'sMuseum Auditorium

Effective: 9 Jun 20

A

B

C

D

E

F

G

H

Extra Time Devoted to Covid-19 Protocols (in Hours)

Date Worked Cost Code Description

Labor Class

Labor Type Hours Worked

Billable Rate Incurred Cost (Column F x G)

3/3/21 INSTALL - BLACK IRON 3/4/21 SUPERVISION - FOREMAN 3/4/21 INSTALL - FRG 3/4/21 INSTALL - FRG 3/4/21 LOAD & DIST - FRG 3/4/21 LOAD & DIST - FRG 3/4/21 INSTALL - BLACK IRON 3/4/21 INSTALL - BLACK IRON 3/5/21 SUPERVISION - FOREMAN

Journeyman

Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter

7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 3 7 7 7 7 7 7 7 7 7

1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 0.47 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09

$123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14

$135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $58.27 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03

Foreman

Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Foreman Foreman Foreman Foreman Foreman Foreman

3/5/21 INSTALL - FRG 3/5/21 INSTALL - FRG

3/5/21 INSTALL -WOOD BLOCKING 3/5/21 INSTALL -WOOD BLOCKING

3/5/21 INSTALL - FRG 3/5/21 INSTALL - FRG

3/8/21 SUPERVISION - FOREMAN

3/8/21 INSTALL - FRG 3/8/21 INSTALL - FRG

3/8/21 INSTALL -WOOD BLOCKING 3/8/21 INSTALL -WOOD BLOCKING

3/8/21 INSTALL - FRG

3/9/21 SUPERVISION - FOREMAN

3/9/21 INSTALL - FRG 3/9/21 INSTALL - FRG 3/9/21 FRAME -WALLS 3/9/21 FRAME -WALLS 3/9/21 INSTALL - FRG 3/9/21 INSTALL - FRG 3/10/21 INSTALL - FRG 3/10/21 INSTALL - FRG 3/10/21 FRAME -WALLS 3/10/21 FRAME -WALLS

3/10/21 SUPERVISION - FOREMAN

3/10/21 INSTALL - BLACK IRON 3/10/21 INSTALL - BLACK IRON 3/11/21 SUPERVISION - FOREMAN 3/11/21 INSTALL -WOOD BLOCKING 3/11/21 INSTALL -WOOD BLOCKING 3/11/21 INSTALL - BLACK IRON 3/11/21 INSTALL - BLACK IRON 3/12/21 SUPERVISION - FOREMAN 3/12/21 INSTALL -WOOD BLOCKING 3/12/21 INSTALL -WOOD BLOCKING 3/11/21 FRAME -WALLS 3/11/21 FRAME -WALLS

3/12/21 FRAME -WALLS 3/12/21 FRAME -WALLS

3/12/21 INSTALL - BLACK IRON 3/12/21 INSTALL - BLACK IRON 3/15/21 SUPERVISION - FOREMAN

Foreman

S pearhead Construction Labor Hours for Covid Procedures

BCM- PV262-AUD - Brooklyn Children'sMuseum Auditorium

Effective: 9 Jun 20

A

B

C

D

E

F

G

H

Extra Time Devoted to Covid-19 Protocols (in Hours)

Date Worked Cost Code Description

Labor Class

Labor Type Hours Worked

Billable Rate Incurred Cost (Column F x G)

3/15/21 INSTALL - FRG 3/15/21 INSTALL - FRG 3/15/21 INSTALL - FRG

Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Foreman Foreman Foreman Foreman Foreman Foreman Foreman

Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter

7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7

1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09

$123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98

$135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14

3/15/21 INSTALL - BLACK IRON 3/15/21 INSTALL - BLACK IRON 3/16/21 SUPERVISION - FOREMAN

3/16/21 INSTALL - FRG 3/16/21 INSTALL - FRG 3/16/21 INSTALL - FRG 3/16/21 INSTALL - FRG

3/16/21 INSTALL - BLACK IRON 3/16/21 INSTALL - BLACK IRON 3/17/21 SUPERVISION - FOREMAN

3/17/21 INSTALL - FRG 3/17/21 INSTALL - FRG

3/17/21 INSTALL - BATT INSULATION 3/17/21 INSTALL - BATT INSULATION 3/17/21 INSTALL - BLACK IRON 3/17/21 INSTALL - BLACK IRON 3/18/21 SUPERVISION - FOREMAN 3/18/21 INSTALL -WOOD BLOCKING 3/18/21 INSTALL -WOOD BLOCKING 3/18/21 INSTALL - GWB OVER 9' 3/18/21 INSTALL - GWB OVER 9' 3/18/21 INSTALL - BLACK IRON 3/18/21 INSTALL - BLACK IRON 3/19/21 SUPERVISION - FOREMAN 3/19/21 INSTALL -WOOD BLOCKING 3/19/21 INSTALL -WOOD BLOCKING 3/19/21 INSTALL - BLACK IRON 3/19/21 INSTALL - BLACK IRON 3/22/21 SUPERVISION - FOREMAN 3/22/21 INSTALL - MISC ITEMS 3/22/21 INSTALL - MISC ITEMS 3/22/21 INSTALL - BLACK IRON 3/22/21 INSTALL - BLACK IRON 3/23/21 SUPERVISION - FOREMAN 3/23/21 INSTALL - MISC ITEMS 3/23/21 INSTALL - MISC ITEMS 3/23/21 INSTALL - BLACK IRON 3/23/21 INSTALL - BLACK IRON 3/23/21 INSTALL - BLACK IRON 3/24/21 SUPERVISION - FOREMAN

3/19/21 INSTALL - GWB (STAND UP BOARDS UP TO 9') 3/19/21 INSTALL - GWB (STAND UP BOARDS UP TO 9')

3/22/21 INSTALL - GWB (STAND UP BOARDS UP TO 9') 3/22/21 INSTALL - GWB (STAND UP BOARDS UP TO 9')

3/24/21 INSTALL - FRG 3/24/21 INSTALL - FRG

3/24/21 INSTALL - BLACK IRON

S pearhead Construction Labor Hours for Covid Procedures

BCM- PV262-AUD - Brooklyn Children'sMuseum Auditorium

Effective: 9 Jun 20

A

B

C

D

E

F

G

H

Extra Time Devoted to Covid-19 Protocols (in Hours)

Date Worked Cost Code Description

Labor Class

Labor Type Hours Worked

Billable Rate Incurred Cost (Column F x G)

3/24/21 INSTALL - BLACK IRON 3/24/21 INSTALL - BLACK IRON 3/24/21 INSTALL - BLACK IRON 3/25/21 SUPERVISION - FOREMAN 3/25/21 INSTALL - BLACK IRON 3/25/21 INSTALL - BLACK IRON 3/25/21 INSTALL - BLACK IRON 3/25/21 INSTALL - BLACK IRON 3/25/21 INSTALL - BLACK IRON 3/25/21 INSTALL - BLACK IRON 3/26/21 INSTALL - BLACK IRON 3/26/21 INSTALL - BLACK IRON 3/29/21 SUPERVISION - FOREMAN 3/29/21 INSTALL -WOOD BLOCKING 3/29/21 INSTALL -WOOD BLOCKING 3/29/21 LOAD & DIST - FRG 3/29/21 LOAD & DIST - FRG 3/29/21 INSTALL - BLACK IRON 3/29/21 INSTALL - BLACK IRON 3/30/21 SUPERVISION - FOREMAN 3/30/21 INSTALL -WOOD BLOCKING 3/30/21 INSTALL -WOOD BLOCKING 3/30/21 INSTALL - BLACK IRON 3/30/21 INSTALL - BLACK IRON 3/31/21 SUPERVISION - FOREMAN 3/26/21 INSTALL - FRG 3/26/21 INSTALL - FRG 3/26/21 INSTALL - FRG 3/26/21 INSTALL - FRG

Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Journeyman Foreman Foreman Foreman Foreman Foreman Foreman Foreman Foreman Foreman

Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter Carpenter

7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7

1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09

$123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $123.98 $132.14 $123.98 $123.98 $123.98 $132.14 $132.14 $123.98 $123.98 $123.98 $123.98 $123.98 $132.14

$135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $135.14 $144.03 $135.14 $135.14 $135.14 $144.03 $144.03 $135.14 $135.14 $135.14 $135.14 $135.14 $144.03

3/31/21 INSTALL - FRG 3/31/21 INSTALL - FRG

3/31/21 INSTALL - BLACK IRON 3/31/21 INSTALL - BLACK IRON 4/1/21 SUPERVISION - FOREMAN

4/1/21 INSTALL - FRG 4/1/21 INSTALL - FRG

4/1/21 INSTALL - BLACK IRON 4/1/21 INSTALL - BLACK IRON 4/2/21 SUPERVISION - FOREMAN

4/2/21 INSTALL - FRG 4/2/21 INSTALL - FRG 4/2/21 INSTALL - FRG

4/5/21 SUPERVISION - FOREMAN 4/6/21 SUPERVISION - FOREMAN

4/6/21 INSTALL - FRG 4/6/21 INSTALL - FRG 4/6/21 INSTALL - FRG

4/6/21 INSTALL - BLACK IRON 4/6/21 INSTALL - BLACK IRON 4/7/21 SUPERVISION - FOREMAN

Foreman