Division 01 - DOC STANDARD GENERAL CONDITIONS SINGLE CONTRACT PROJECTS Issue Date June 01, 2013 Revised - January 15, 2015

-3.--=.......,.. DESIGN + CONSTRUCTION

combination thereof. Such entity may be either an employee(s) of the City or an entity engaged by the City to provide such services.

C. Submittals: Written and graphic information that requires responsive actions and includes without limitation all shop drawings, product data, letters of certification, tests and other information required for quality control and as required by the Contract Documents.

D. Informational Submittals: Written information that does not require responsive action. Submittals may be rejected for non-compliance with the Contract.

E. Shop Drawings: Include drawings, diagrams, illustrations, schedules, performance charts, brochures, and other data, except for coordination drawings, specifically prepared for the project by the Contractor or any subcontractor, manufacturer, supplier or distributor, which illustrates how specific portions of the work shall be fabricated and/or installed.

F. Coordination Drawings: As required in Section 01 31 00 PROJECT MANAGEMENT AND COORDINATION.

G. Product Data and Quality Assurance Submittals: Includes manufacturer's standard catalogs, pamphlets and other printed materials including without limitation the following:

1.

Catalogue and Product specifications

2. 3. 4. 5. 6. 7. 8. 9.

Installation instructions

Color charts Catalog cuts

Rough-in diagrams and templates

Wiring diagrams

Performance curves

Operational range diagrams

Mill reports 10. Design data and calculations

11. Certification of compliance or conformance 12. Manufacturer's instructions and field reports

1.5 COORDINATIONDRAWINGS:

A. The Contractor shall provide reproducible Coordination Drawing(s) of the reflective ceiling showing the integration of all applicable contract work, including general construction work as well as trade work (Plumbing, HVAC, and Electrical) to be performed by subcontractors. The Coordination Drawing(s) shall include, without limitation, the following information: 1. General Construction work showing the reflective ceiling plan including starting points, ceiling and beam soffits elevations, ceiling heights, roof openings, etc. 2. HVAC Contract work showing ductwork, heating and sprinkler piping, location of grilles, registers etc. and access doors in hung ceilings. Locations shall be fixed by elevations and dimensions from column centerlines and/or walls. 3.. Plumbing Contract work including piping, valves, cleanouts etc., indicating locations and elevations and shall indicate the necessary access doors. 4. Electrical Contract work indicating fixtures, large conduit runs, clearances, pull boxes, junction boxes, sound system speakers, etc. B. The Contractor shall issue the completed Coordination Drawing(s) to the Resident Engineer for his/her review. The Resident Engineer may call as many meetings as necessary with the Contractor, including

SUBMITTAL PROCEDURES 01 33 00 - 2