NYC AGENCY RENOVATION & REHAB CITY OWNED BUILDINGS/STRUCTURES PLA overtime or schedule overtime as to some, but not all, of the crafts and whether or not of a

continuous nature.

SECTION 3. SHIFTS

A.

Flexible Schedules - Scheduling of shift work, including Saturday

and Sunday work, shall be within the discretion of the Contractor in order to meet Program

Work schedules and existing Program Work conditions including the minimization of

interference with the mission of the Agency. It is not necessary to work a day shift in order

to schedule a second or third shift, or a second shift in order to schedule a third shift, or to

schedule all of the crafts when only certain crafts or employees are needed. Shifts must

have prior approval of the Agency or Construction Manager, and must be scheduled with

not less than five work days notice to the Local Union or such lesser notice as may be

mutually agreed upon.

B.

Second and/or Third Shifts/Saturday and/or Sunday Work - - The

second shift shall start between 3 p.m. and 6 p.m. and the third shift shall start between 11

p.m. and 2 a.m., subject to different times necessitated by the Agency phasing plans on

specific projects. There shall be no reduction in shift hour work. With respect to second

and third shift work there shall be a 5% shift premium. No other premium or other

payments for such work shall be required unless such work is in excess of the employee's

regularly scheduled work week, i.e., 40 hours in the week or thirty five (35) or thirty seven

and one half (37 ½) pursuant to Article 12, section l(A). All employees within a

classification performing Program Work will be paid at the same wage rate regardless of

the shift or work scheduled work, subject only to the foregoing provisions.