Division 01 - DDC STANDARD GENERAL CONDITIONS SINGLE CONTRACT PROJECTS Issue Date June 01, 2013 Revised - January 15, 2015
~,w-cnv"""""""°'
DESIGN + CONSTRUCTION
20. VENTILATION: Provide manufacturer's cut sheets for the following:
a. Carbon dioxide monitoring systems, if any, installed to measure outside air delivery. b. Air filters: for detailed requirements refer to Section 01 81 19 INDOOR AIR QUALITY REQUIREMENTS. 21. REFRIGERATION: For all refrigeration equipment, provide manufacturer's cut sheets indicating the following: a. Equipment type. b. Equipment life. Default values specified by the 2007 ASHRAE Applications Handbook will be used unless otherwise demonstrated by the manufacturer's guarantee and an equivalent long-term service contract. c. Refrigerant type. d. Refrigerant charge in pounds of refrigerant per ton of gross cooling capacity. e. Tested refrigerant leakage rate, in percent per year. A default rate of 2% will be used unless otherwise demonstrated by test data. f. Tested end-of-life refrigerant loss, in percent. A default rate of 10%will be used unless otherwise demonstrated by test data.
1.7 LEED BUILDINGSUBMITTAL REQUIREMENTS:
A. The LEED BUILDING Submittal information shall be assembled into one package per contract specification section(s) (or per subcontractor), and submitted in accordance with Section 01 33 00, SUBMITTAL PROCEDURES. Incomplete or inaccurate LEED BUILDING submittals may be used as the basis for the rejection of products or assemblies. Incomplete or inaccurate LEED BUILDING Submittals may be used as the basis for rejecting the submitted products or assemblies.
1.8 LEEDACTION PLANS:
A. Construction Waste Management Plan- Refer to Section 01 74 19, Construction Waste Management and Disposal for detailed submittal requirements.
B. Construction IAQ Management Plan- Refer to Section 01 81 19, Indoor Air Quality Requirements for LEED Buildings, for detailed submittal requirements. C. Erosion and Sedimentation Control Plan: 1. The Plan shall be in accordance with the New York State Department of Environmental Conservation (NYSDEC) or the 2003 EPA Construction General Permit, whichever is more stringent. 2. The Plan shall be submitted in accordance with Section 01 33 00, SUBMITTAL PROCEEDURES. 3. Detailed requirements: ESC Plan a. Include the Stormwater Pollution Prevention Plan, if required. b. Identify the party responsible for Plan monitoring and documentation. The party must be regularly on site. c. Describe all site work that will be implemented on the project. d. Provide site plan with location of ESC measures, including, but not limited to, stormwater quantity controls, stormwater quality controls, stabilized construction entrances, washdown areas, and inlet/catch basin protection. e. Describe the inspection and maintenance of the ESC measures. Provide a construction schedule indicating weekly site review. f. Describe reporting and documentation measures. 4. Detailed requirements: ESC Measures
SUSTAINABLE DESIGN REQUIREMENTS FOR LEED BUILDINGS 018113-7